Friday, September 25, 2015

Progress Update - 9/26/15



  • Erosion Repair Work:
    • Areas that had erosion due to significant rainfall are currently being repaired. Several areas on the front 9 are complete and majority of those areas the turf that was installed was able to be reused. The contractor has a 5-6 man team assisting with the repair work. We are projecting the erosion repair work to be finished by the week of October 19th.
  • Bridge Work:
    • All the bridges have had new guard railings installed and the sides have been stained with a fresh coat of paint. The railings will not be stained brown in the future however we will plan on applying a sealer on a yearly basis
  • Lakes on hole #5 & #14:
    • Due to the disturbance of the earth to those two lakes in particular, we continue to battle algae. We are implementing an environmentally friendly dye to help shade the lake and block the sunlight from reaching the soil under the water. The aquatic maintenance team have also been treating the lakes and are now introducing a microbial treatment. 
    • We are still optimistic that a majority of the cypress trees located on the 5 newly created islands will survive the environmental change that they have went through. In the event that a few may need to be replaced, 5 green buttonwoods have been installed as a potential replacement.  
    • Additional aquatic plants are also being considered as they aide in filtrating the water and shade the soil similar to the dye. 


Did you know:

Before the renovation the square footage of the bunkers was 145,000 and the square footage on the newly renovated Heron is 103,000.

55 days until the Opening Day = Friday, November 20th


Member Course Tours:

Thursday, October 8th @ 1:00


Should you have any question or comments, please feel free to send them to heron@theoaksclub.com or call the Heron Hotline at 966-6940 


Progress Video:

Click Here to view the Progress video
Password = "oaks"



The Heron Implementation Team

Saturday, August 22, 2015

Progress Update #51 - Week 53 - 8/22/15


Week 53  

  • The contractor continues to work on punch list tasks.
    • Southeastern Golf will assist with erosion repair after they have completed their punch list task.
  • The Green and Grounds team mowed #15 fairway for the first time since the grass installation
    • The fairways, tees, and approaches on holes 3-8, 11-17 are being mowed on a routine basis.
  • All the greens were topdressed and also aerated.
  • This week we will begin to aerating the fairway on hole #3.

Did you know:

There were over 1,800 landscape plants installed on the berm that separates hole #18 from driving range.

Member Course Tours:

Wednesday, August 26th @ 1:30 pm


Should you have any question or comments, please feel free to send them to heron@theoaksclub.com or call the Heron Hotline at 966-6940 



*Please know that the entire Heron Golf Course is a construction zone. To Ensure your safety, please do not access the Heron course at any time. Should you see anyone out walking or driving on the course not accompanied by Management, please notify the Golf Shop or Security.



Progress Video:

Click Here to view the Week #53 Progress



The Heron Implementation Team

Friday, August 14, 2015

Progress Update #50 - Week 52 - 8/14/15


Week 52 Accomplishments 

  • Grassing = 100% Complete
  • Bunker Construction = 100% Complete



Upcoming Week Goals:
  • Contractor is to start the punch list 
  • Start the construction of the Heron Putting green which is apart of the Member approved plan.


    Did you know:

    • The greens are grassed with TifEagle Bermudagrass
    • The collars and chipping surrounds are grassed with TifGrand Bermudagrass
    • The fairways, tees, and roughs are grassed with Celebration Bermudagrass
    • There are several miscellaneous rough areas that are grassed with Argentine Bahiagrass



    Member Course Tours:

    Wednesday, August 26th @ 1:30 pm


    Should you have any question or comments, please feel free to send them to heron@theoaksclub.com or call the Heron Hotline at 966-6940 



    *Please know that the entire Heron Golf Course is a construction zone. To Ensure your safety, please do not access the Heron course at any time. Should you see anyone out walking or driving on the course not accompanied by Management, please notify the Golf Shop or Security.



    Progress Video:

    Click Here to view the Week #50 Progress



    The Heron Implementation Team

    Friday, August 7, 2015

    Progress Update #49 - Week 51 - 8/7/15


    Week 51 Accomplishments 

    • Grassing:
      • Hole #1 - 95% complete
      • Hole #9 - 100% complete
      • Hole #2 - Sod has been laid around the tee complex and continues around the bunkers
    • Bunker Construction:
      • Hole #1 - 100% complete
      • Hole #2 - 90% complete (sand installation will be completed on Saturday, August 8th)

    Upcoming Week Goals:
    • Grassing: 
      • Hole #2 - complete the remaining grass installation by Wednesday, August 12th.
    • Southeastern Golf will begin the punch-list that has been created by Jason Straka (Course Architect) and Joe Voss (Project Manager).


    Did you know:

    A year ago the 2nd grass eradication application was being applied to the course.


    Member Course Tours:

    Wednesday, August 12th @ 1:30 PM


    Should you have any question or comments, please feel free to send them to heron@theoaksclub.com or call the Heron Hotline at 966-6940 



    *Please know that the entire Heron Golf Course is a construction zone. To Ensure your safety, please do not access the Heron course at any time. Should you see anyone out walking or driving on the course not accompanied by Management, please notify the Golf Shop or Security.



    Progress Video:

    Click Here to view the Week #50 Progress



    The Heron Implementation Team

    Friday, July 31, 2015

    Progress Update #48 - Week 50 - 7/31/15


    Week 50 Accomplishments 

    • Grassing:
      • Hole #1 - Sod is being laid around the lake banks and bunker edges
      • Hole #9
        •  Sod has around the lake edges and the fairway bunker edge
        • Sprigging is scheduled to take place on 
    • Bunker Construction:
      • Hole #1
        • Fairway & one of the green side bunkers are complete
      • Hole #9
        • Fairway Bunker is complete
      • Hole #2
        • The right-hand fairway bunkers are currently being shaped and prepared for drainage

        Upcoming Week Goals:
        • Grassing: 
          • Hole #1
            • Sprigging is tentatively scheduled for Monday, August 3rd 
          • Hole #2
            • Tentatively scheduled to be completely grassed by the end of the week. (WEATHER PERMITTING)
        • Bunker Construction:
          • Hole #2 - Complete all the bunkers on #2


        Did you know:

        For the month of July we've recorded a total of 12.62 inches as of 4:00 PM on July 31st. Half of that total has fallen in the last 7.5 days.


        Member Course Tours:

        Wednesday, August 12th @ 1:30 PM


        Should you have any question or comments, please feel free to send them to heron@theoaksclub.com or call the Heron Hotline at 966-6940 



        *Please know that the entire Heron Golf Course is a construction zone. To Ensure your safety, please do not access the Heron course at any time. Should you see anyone out walking or driving on the course not accompanied by Management, please notify the Golf Shop or Security.



        Progress Video:

        Click Here to view the Week #50 Progress
        password = oaks 


        The Heron Implementation Team

        Friday, July 24, 2015

        Progress Update #47 - Week 49 - 7/24/2015


        Week 49 Accomplishments 

        • Grassing:
          • Hole #1 - Tee Complex is 100% grassed
          • Hole #9
            • Green Complex is 100% grassed
            • Sod has been laid along a portion of the lake bank
          • Hole #10 - 95% grassed
          • Hole #11 - Tee Complex is 100% grassed
          • Bunker Construction:
            • Hole #9
              • Fairway - 50% complete
            • Hole #1
              • Fairway bunker 40% complete
            • Hole #10 - All bunkers are 100% complete
          • Landscape Installation
            • Additional Bougainvilleas have been planted between #1 tees and #9 Green Complex
            • Ornamental Grasses have been planted on the back side of the left hand fairway and green-side  bunkers.
            • Two large oaks trees have been planted near #10 green cartpath and #11 tee complex.

              Upcoming Week Goals:
              • Grassing: 
                • Holes #1 - Sod and Sprig the all remaining areas
                  • (Goal by the end of the week is to be 100% complete) 
                • Hole #9 - Sod and Sprig the fairway portion of the hole 
                  • (Goal by the end of the week is to be 100% complete)
              • Bunker Construction:
                • Complete Better Billy Bunker liner and sand installation on #9 Fairway, #1 Fairway, and #1 Green-side.

              Look Ahead:
              • The week of August 3rd:
                • Complete the grassing on hole #2 (Final hole!).
                • Start to complete the close-out punch list 
              • The week of August 10th:
                • Complete punch list items and begin to reduce construction staff and equipment.



              Did you know:

              The 1st phase of greens have been taken off the "grow-in" agronomic program and are now being maintained as if they are nearly ready for play. All greens are being mowed at the same height of cut and are being mowed at a minimum of 3 - 4 times a week. 


              Member Course Tours:

              Wednesday, July 29th @ 1:30 pm



              Should you have any question or comments, please feel free to send them to heron@theoaksclub.com or call the Heron Hotline at 966-6940 



              *Please know that the entire Heron Golf Course is a construction zone. To Ensure your safety, please do not access the Heron course at any time. Should you see anyone out walking or driving on the course not accompanied by Management, please notify the Golf Shop or Security.



              Progress Video:

              Click Here to view the Week #49 Progress
              password = oaks 


              The Heron Implementation Team

              Saturday, July 18, 2015

              Progress Update #46 - Week 48 - 7/18/2015


              Week 48 Accomplishments 

              • Grassing:
                • Hole #18 - All areas are complete
                • Hole #1 - Sod has been laid around of the lake bank along the tee complex and other specific areas
                • Hole #9 - Sod has been laid around the bunkers and lake bank at the green complex
                • Bunker Construction:
                  • Hole #9
                    • Green-side - 100% complete
                  • Hole #10
                    • Fairway and Green-side bunkers are shaped and drainage piping and gravel are being installed.
                • Landscape Installation
                  • Oleanders and Fountain Grass have been installed under the 8 Shady Lady Olive trees to the left of #10 Tees.
                  • Bougainvilleas have been installed behind #10 tees around 3 Bismarck palms.
                  • 2 Live Oaks have been installed behind and to the left of #10 green 

                    Upcoming Week Goals:
                    • Grassing: 
                      • Due to the inclement weather on Thursday and Friday, grassing of the below areas have been rescheduled for Monday, July 20th
                        • Holes #1 - Sod and Sprig the Tee Complex 
                        • Hole #9 - Sod and Sprig Green surrounds and fairway area of the green side of the lake
                        • Hole #10 - Sod and Sprig Tee complex 
                      • Hole #10 & #11 tee complex - complete later in the week
                    • Bunker Construction:
                      • Complete Better Billy Bunker liner and sand installation on holes #10, #9 Fairway, and #1 Fairway.

                    Did you know:

                    Since Monday, July 13th, The Oaks Club has received approximately 4.25 inches of rain as of Friday, July 17th. 


                    Member Course Tours:

                    Wednesday, July 29th @ 1:30 pm



                    Should you have any question or comments, please feel free to send them to heron@theoaksclub.com or call the Heron Hotline at 966-6940 



                    *Please know that the entire Heron Golf Course is a construction zone. To Ensure your safety, please do not access the Heron course at any time. Should you see anyone out walking or driving on the course not accompanied by Management, please notify the Golf Shop or Security.



                    Progress Video:

                    Due to inclement weather on Thursday and Friday, a Progress Video will be produced and distributed on Monday, July 20th. 


                    The Heron Implementation Team

                    Friday, July 10, 2015

                    Progress Update #45 - Week 47 - 7/10/15


                    Week 47 Accomplishments 

                    • Grassing:
                      • Hole #18 - All sod work will be completed by Saturday, 7/11/15.
                      • Hole #1 - Sod has been laid on 75% of the lake bank along the tee complex
                      • Bunker Construction:
                        • Hole #18
                          • Fairway
                            • All bunkers have Better Billy Bunker liner installed
                            • remaining bunkers are in the process of having bunker sand installed
                        • Hole #9
                          • Green-side
                            • Drainage and Gravel installation is 85% complete
                      • Landscape Installation
                        • Native grasses installed along the upper portion to of the fairway bunkers on the left side.
                        • 8 Shady Lady Olive trees have been installed as a buffer from #10 tee and the driving range buffer
                        • Ferns are being installed under the large oaks behind #17 green

                          Upcoming Week Goals:
                          • Grassing: 
                            • Hole #18 - Sprig the remaining areas on Monday, 7/13
                            • Holes #1 - Sod and Sprig the Tee Complex 
                            • Hole #9 - Sod and Sprig Green surrounds and fairway area of the green side of the lake
                            • Hole #10 - Sod and Sprig Tee complex 
                          • Bunker Construction:
                            • Hole #18 - Complete the remaining bunkers
                            • Hole #10 - Start the shaping, drainage, and bunker liner installation
                          • Finish Shaping
                            • Hole #10 / #9 / #1 - Continue to box blade in preparation for grassing
                          • Landscape Installation will continue at the beginning of the week

                          Did you know:

                          The Shady Lady Olive Tree can reach 30 feet in height and are considered a "non-messy" tree. 


                          Member Course Tours:

                          Tuesday, July 14th @ 10:00 am



                          Should you have any question or comments, please feel free to send them to heron@theoaksclub.com or call the Heron Hotline at 966-6940 



                          *Please know that the entire Heron Golf Course is a construction zone. To Ensure your safety, please do not access the Heron course at any time. Should you see anyone out walking or driving on the course not accompanied by Management, please notify the Golf Shop or Security.



                          Progress Video:

                          Click Here to view the Progress Video
                          Password: "oaks"


                          The Heron Implementation Team

                          Friday, July 3, 2015

                          Progress Update #44 - Week 46 - 7/3/2015


                          Week 46 Accomplishments 

                          • Grassing:
                            • Hole #15 is completely grassed
                            • Tee complex on #9 is 95% Complete & Hole #18 is 100% complete
                          • Bunker Construction:
                            • Hole #18
                              • Green-side  
                                • Better Billy Bunker Liner and Sand installed
                              • Fairway
                                • 2 bunkers have Better Billy Bunker installed
                                • remaining bunkers are in the process of being shaped, drainage installation, and / or Better Billy Bunker Liner being installed.

                            Upcoming Week Goals:
                            • Grassing: 
                              • Hole #18 - Complete the remaining areas  
                            • Bunker Construction:
                              • Hole #18 - Complete the remaining bunkers
                              • Hole #10 - Start the shaping, drainage, and bunker liner installation
                            • Finish Shaping
                              • Hole #10 / #9 / #1 - Continue the bulldozer work on these three holes  

                            Did you know:

                            It takes a golf course sprinkler approximately 3 minutes to make a complete 360 degree rotation.


                            Member Course Tours:

                            No Tours are scheduled the week of July 6th



                            Should you have any question or comments, please feel free to send them to heron@theoaksclub.com or call the Heron Hotline at 966-6940 



                            *Please know that the entire Heron Golf Course is a construction zone. To Ensure your safety, please do not access the Heron course at any time. Should you see anyone out walking or driving on the course not accompanied by Management, please notify the Golf Shop or Security.



                            Progress Video:

                            Click Here to view the Progress Video



                            The Heron Implementation Team

                            Friday, June 26, 2015

                            Progress Update #43 - Week 45 - 6/26/2015


                            Week 45 Accomplishments 

                            • Grassing:
                              • All Greens, Collars, Approaches, and Chipping areas have been grassed
                                • Greens = TifEagle Bermuda
                                • Collars, Approaches, and Chipping Areas = TifGrand Bermuda
                            • Bunker Construction:
                              • Hole #15
                                • Green-side Bunker is complete
                                • Fairway Waste Bunker is 90% complete
                            • Cartpath Installation:
                              • All Cartpaths are complete

                              Upcoming Week Goals:
                              • Grassing: 
                                • Hole #15 - Monday & Tuesday
                                • Hole #18 Tee Complex - Wednesday or Thursday
                                • Hole #9 Tee Complex - Wednesday or Thursday
                              • Bunker Construction:
                                • Hole #18 - Complete the Better Billy Bunker Liner installation and install the G-Angle Bunker Sand

                              Did you know:

                              • The Project remains on Time and on Budget!
                              • All areas which are utilized for material storage and/or course entry points will be refurbished to a better condition than when they were originally used for prior to construction beginning. The contractor is obligated per the contract with Club to do so at the conclusion of the project.


                              Member Course Tours:

                              Wednesday, July 1st @ 1:30 PM


                              Should you have any question or comments, please feel free to send them to heron@theoaksclub.com or call the Heron Hotline at 966-6940 



                              *Please know that the entire Heron Golf Course is a construction zone. To Ensure your safety, please do not access the Heron course at any time. Should you see anyone out walking or driving on the course not accompanied by Management, please notify the Golf Shop or Security.



                              Progress Video:

                              Click Here to view the Progress Video
                              Password = oaks


                              The Heron Implementation Team

                              Friday, June 19, 2015

                              Progress Update #42 - Week 44 - 6/19/2015


                              Week 44 Accomplishments 

                              • Bunker Construction:
                                • Hole #15 
                                  • Green-side Bunker -  ready for drainage installation and then Better Billy Bunker liner installation
                                  • Waste Bunker along the fairway is 60% complete
                                • Hole #18 - Green-side bunkers are being shaped 
                              • Grassing:
                                • 12 holes are 95% grassed or fully complete.
                                • Remaining Order of holes:16, 15, 18, 10, 9, 1, 2 
                                • Holes #17
                                  • All areas have been grassed 
                              • Cartpath Installation:
                                • Hole #1 & #2 - Complete

                                Upcoming Week Goals:
                                • Grassing: 
                                  • Celebration Bermudagrass
                                    • Complete hole #16
                                  • TifGrand Bermudagrass
                                    • Complete holes 15, 18, 10, 9, 1, and 2
                                  • TifEagle (Greens)
                                    • Complete holes 15, 18, 10, 9, 1, and 2
                                • Bunker Construction:
                                  • Install drainage and Better Billy Bunker in the green-side bunker on #15
                                  • Continue Bunker shaping around the #18 Green

                                Did you know:

                                The large concrete structure located on hole #2 was intended to be used as replacement for the weir structure in the lake on hole #7. Instead the structure that is there was modified and thus the structure on hole #2 is going to be returned.


                                Member Course Tours:

                                Wednesday, June 24th @ 10:30 AM



                                Should you have any question or comments, please feel free to send them to heron@theoaksclub.com or call the Heron Hotline at 966-6940 



                                *Please know that the entire Heron Golf Course is a construction zone. To Ensure your safety, please do not access the Heron course at any time. Should you see anyone out walking or driving on the course not accompanied by Management, please notify the Golf Shop or Security.



                                Progress Video:

                                Click Here to view the Progress Video
                                Password = oaks


                                The Heron Implementation Team

                                Friday, June 12, 2015

                                Progress Update #41 - Week 43 - 6/12/15


                                Week 43 Accomplishments 

                                • Greens:
                                  • Regrading and checking the rootzone depth
                                    • Holes 1, 2, 9, & 10 - Complete
                                • Bunker Construction:
                                  • Hole #17 Fairway Bunkers - Drainage installation and Better Billy Bunker liner is either in the process if being complete or is complete.
                                • Grassing:
                                  • Order of holes: 3 - 8, 11 - 18, 10, 9, 1, 2 
                                  • Order of installation 
                                    • Sodding around bunkers / lake banks / drains
                                    • TifGrand Bermuda - Collars, Approaches, and Chipping areas
                                    • Celebration Bermuda Sprigs - Fairways, Roughs, and Tees
                                  • Greens - Phase #2 of 3 - #11, 12, 13, 14, 16, & 17 = complete
                                  • Holes #14
                                    • All areas have been grassed 

                                  Upcoming Week Goals:
                                  • Grassing: 
                                    • Celebration Bermudagrass  
                                      • Sprig and Sod Holes #16 & #17
                                  • Bunker Construction:
                                    • Install drainage and Better Billy Bunker in the green-side bunker on #15
                                    • Install drainage in the waste bunker on the left side of hole #15

                                  Did you know:

                                  The first and second phase of greens grassing are 81,056 square feet or 1.86 acres. The old Heron greens were slightly over 130,680 square feet or 3 acres.


                                  Member Course Tours:

                                  Wednesday, June 17th @ 1:30 PM



                                  Should you have any question or comments, please feel free to send them to heron@theoaksclub.com or call the Heron Hotline at 966-6940 



                                  *Please know that the entire Heron Golf Course is a construction zone. To Ensure your safety, please do not access the Heron course at any time. Should you see anyone out walking or driving on the course not accompanied by Management, please notify the Golf Shop or Security.



                                  Progress Video:

                                  Click Here to view the Progress Video




                                  The Heron Implementation Team

                                  Friday, June 5, 2015

                                  Progress Update #40 - Week 42 - 6/5/2015


                                  Week 42 Accomplishments 

                                  • Greens:
                                    • Regrading and checking the rootzone depth
                                      • Holes 16, 17, & 18 - Complete
                                  • Bunker Construction:
                                    • Hole #16 & #17 Greenside Bunkers - Drainage installation and Better Billy Bunker liner installed in the green-side bunker
                                  • Grassing:
                                    • Order of holes: 3 - 8, 11 - 18, 10, 9, 1, 2 
                                    • Order of installation 
                                      • Sodding around bunkers / lake banks / drains
                                      • TifGrand Bermudagrass - Collars, Approaches, and Chipping areas
                                      • Celebration Sprigs
                                    • Holes #12
                                      • All areas have been grassed with the exception of the green
                                    • Holes #14, 16, & 17
                                      • TifGrand Bermudagrass installed - Collars, Approach Areas, and Chipping Areas

                                    Upcoming Week Goals:
                                    • Grassing: 
                                      • Celebration Bermudagrass  
                                        • Sprig and Sod Holes #14 & half  of #17
                                      • TifEagle - Greens
                                        • Holes #11, 12, 13, 14, 16, & 17
                                    • Bunker Construction:
                                      • Install Drainage and Better Billy Bunker in the fairway bunkers on #17 and the green-side bunker on #15


                                    Did you know:

                                    The course will be Cartpath Only for at least 3 months to allow the turf to fully mature during the slower growing period (Winter Months).


                                    Member Course Tours:

                                    Wednesday, June 10th @ 1:30 PM



                                    Should you have any question or comments, please feel free to send them to heron@theoaksclub.com or call the Heron Hotline at 966-6940 



                                    *Please know that the entire Heron Golf Course is a construction zone. To Ensure your safety, please do not access the Heron course at any time. Should you see anyone out walking or driving on the course not accompanied by Management, please notify the Golf Shop or Security.



                                    Progress Video:

                                    Click Here to view the Progress Video
                                    Password = "oaks"



                                    The Heron Implementation Team

                                    Friday, May 29, 2015

                                    Progress Update #39 - Week 41 - 5/29/15


                                    Week 41 Accomplishments 

                                    • Greens:
                                      • Regrading and checking the rootzone depth
                                        • Hole # 15 - Complete
                                    • Bunker Construction:
                                      • Hole #14 - Drainage installation and Better Billy Bunker liner installed in the green-side bunker
                                    • Grassing:
                                      • Order of holes: 3 - 8, 11 - 18, 10, 9, 1, 2 
                                      • Order of installation 
                                        • Sodding around bunkers / lake banks / drains
                                        • TifGrand Bermudagrass - Collars, Approaches, and Chipping areas
                                        • Celebration Sprigs
                                      • Holes #13
                                        • All areas have been grassed with the exception of the green

                                    Upcoming Week Goals:
                                    • Grassing: Sprig and Sod Holes #12 & #14 except for the greens
                                    • Complete Landscape installation along #3 roadway
                                    • Complete the cartpath installation on hole #1 


                                    Did you know:

                                    One of the golf course sprinklers irrigates approximately 3,100 square feet. 


                                    Member Course Tours:

                                    Dates and Time:

                                    No tours are scheduled for this coming week


                                    Should you have any question or comments, please feel free to send them to heron@theoaksclub.com or call the Heron Hotline at 966-6940 



                                    *Please know that the entire Heron Golf Course is a construction zone. To Ensure your safety, please do not access the Heron course at any time. Should you see anyone out walking or driving on the course not accompanied by Management, please notify the Golf Shop or Security.



                                    Progress Video:

                                    Click Here to view the Progress Video




                                    The Heron Implementation Team

                                    Friday, May 22, 2015

                                    Progress Update #38 - Week 40 - 5/22/2015


                                    Week 40 Accomplishments 

                                    • Greens:
                                      • Regrading and checking the rootzone depth
                                        • Hole # 13 - Complete
                                        • Hole #14 - Complete
                                      • Grassing complete on holes #3 - #8
                                    • Bunker Construction:
                                      • Hole #13 - Drainage installation and Better Billy Bunker liner installed in the green-side bunker
                                    • Grassing:
                                      • Order of holes: 3 - 8, 11 - 18, 10, 9, 1, 2 
                                      • Order of installation 
                                        • Sodding around bunkers / lake banks / drains
                                        • TifGrand Bermudagrass - Collars, Approaches, and Chipping areas
                                        • Celebration Sprigs
                                      • Holes #8
                                        • All areas have been grassed
                                      • Hole #11
                                        • All areas have been grassed from the bridge to the green
                                    • Landscape Installation:
                                      • Hole #17
                                        • Bougainvillea, Oleanders, Firebush, and Ornamental grasses have been installed on the berm behind the green. Additional ferns are to be installed under the large oaks along the road.
                                      • Hole #13
                                        • Ornamental Grasses installed behind the left fairway bunker.
                                    • Fumigation on Tees
                                      • Complete on the holes - #1, 10, 14, 15, and 18
                                      • Tarps will be removed the early part of next week

                                    Upcoming Week Goals:
                                    • Grassing: 
                                      • Sprig and Sod from the bridge back to the tee on Hole #13.
                                      • Sprig and Sod all of hole #12 except for the green
                                    • Complete bunker drainage installation, Better Billy Bunker Liner, and sand installation on Hole #14
                                    • Complete Landscape installation along #3 roadway
                                    • Complete the cartpath installation on holes #1 and #9



                                    *The contractor will not be working on Monday due to the holiday




                                    Golf Course Architect, Jason Straka's next scheduled site visits are:

                                    1) May 27th - May 28th 


                                    Did you know:

                                    The greens will be firm during the first year due to lack of a thatch or mat layer which is located right below the putting surface.


                                    Member Course Tours:

                                    Dates and Time:

                                    Thursday, May 28th @ 9:30 am


                                    Should you have any question or comments, please feel free to send them to heron@theoaksclub.com or call the Heron Hotline at 966-6940 



                                    *Please know that the entire Heron Golf Course is a construction zone. To Ensure your safety, please do not access the Heron course at any time. Should you see anyone out walking or driving on the course not accompanied by Management, please notify the Golf Shop or Security.



                                    Progress Video:

                                    Click Here to view the Progress Video
                                    Password - "oaks"



                                    The Heron Implementation Team


                                    Friday, May 15, 2015

                                    Progress Update #37 - Week 39 - 5/15/2015


                                    Week 39 Accomplishments:
                                    • Greens:
                                      • Regrading and checking the rootzone depth:
                                        • Hole #11 - Complete
                                        • Hole #12 - Complete
                                    • Cartpath Installation  
                                      • No cart path was installed this week.
                                      • Remaining holes to complete
                                        • Holes #1, #9, #2, and #18 
                                      • Bunker Construction
                                        • Finish shaping:
                                          • Hole#14 - Complete
                                          • Grassing
                                            • Order of holes: 3 - 8, 11 - 18, 10, 9, 1, 2
                                            • Order of installation: 
                                              • Sodding around bunkers / lake banks / drains
                                              • TifGrand Collars and Approach areas
                                              • Celebration Sprigs
                                            • Hole #6 & #7
                                              • All Areas have been grassed
                                          • Landscape Installation
                                            • There was no landscaping installed this week
                                            • Holes still scheduled to have plant material installed are:
                                              • #3 Roadway
                                              • #2 Roadway
                                              • #17 Green Surround Berm & southern perimeter along roadway
                                              • #18 Green surround
                                              • #10 Tee and Fairway Bunker 

                                          Upcoming Week Goals:
                                          • Sprig & Sod TifGrand Collars and Approach areas holes #11 - #13
                                          • Sprig Celebration on holes #8 and #11 
                                          • Complete the Better Billy Bunker liner installation on hole #13 and & #14
                                          • Sprig TifEagle Bermudagrass on Greens #3 - #8
                                            • Thursday, May 21st
                                          • Complete Fumigation of Tees
                                            • Holes: #14, #15, #18, #10, #1

                                          A Look Ahead:
                                          • Grassing Projected Schedule:
                                            • Week of May 18th
                                              • Complete all grassing on hole #8 & 2/3 of #11 (bridge to green)
                                              • Complete greens grassing on holes #3 - #8
                                              • Complete TifGrand Bermudagrass installation on holes #11, #12, and #13
                                            • Week of May 25th 
                                              • Complete all grassing on holes #12 & #13

                                          Golf Course Architect, Jason Straka's next scheduled site visits are:   

                                          1) May 18th - May 20th

                                          2) May 27th - May 28th



                                          Did you know:  

                                            The east side of the putting green (closest to Heron #1 & #10 tees) will be renovated to match the new Heron putting greens. The existing rootzone mix will be removed and new material will be installed to match the Heron. There will also be a collar of TifGrand Bermudagrass around the TifEagle putting surface, again to mimic the Heron Green Complexes.

                                            Member Course Tours: 

                                            Dates & Time:

                                            1) Monday, May 18th @ 2:30 pm

                                            2) Thursday, May 28th @ 9:30 am




                                            Should you have any questions or comments, please feel free to send them to heron@theoaksclub.com or call the Heron Hotline at 966-6940.



                                            *Please know that the entire Heron Golf Course is a construction zone.  To ensure your safety, please do not access the Heron course at any time



                                            Progress Video:

                                            Password = oaks



                                            The Heron Implementation Team