Week 43 Accomplishments 

  • Greens:
    • Regrading and checking the rootzone depth
      • Holes 1, 2, 9, & 10 - Complete
  • Bunker Construction:
    • Hole #17 Fairway Bunkers - Drainage installation and Better Billy Bunker liner is either in the process if being complete or is complete.
  • Grassing:
    • Order of holes: 3 - 8, 11 - 18, 10, 9, 1, 2 
    • Order of installation 
      • Sodding around bunkers / lake banks / drains
      • TifGrand Bermuda - Collars, Approaches, and Chipping areas
      • Celebration Bermuda Sprigs - Fairways, Roughs, and Tees
    • Greens - Phase #2 of 3 - #11, 12, 13, 14, 16, & 17 = complete
    • Holes #14
      • All areas have been grassed 

    Upcoming Week Goals:
    • Grassing: 
      • Celebration Bermudagrass  
        • Sprig and Sod Holes #16 & #17
    • Bunker Construction:
      • Install drainage and Better Billy Bunker in the green-side bunker on #15
      • Install drainage in the waste bunker on the left side of hole #15

    Did you know:

    The first and second phase of greens grassing are 81,056 square feet or 1.86 acres. The old Heron greens were slightly over 130,680 square feet or 3 acres.


    Member Course Tours:

    Wednesday, June 17th @ 1:30 PM



    Should you have any question or comments, please feel free to send them to heron@theoaksclub.com or call the Heron Hotline at 966-6940 



    *Please know that the entire Heron Golf Course is a construction zone. To Ensure your safety, please do not access the Heron course at any time. Should you see anyone out walking or driving on the course not accompanied by Management, please notify the Golf Shop or Security.



    Progress Video:

    Click Here to view the Progress Video




    The Heron Implementation Team