Week 44 Accomplishments 

  • Bunker Construction:
    • Hole #15 
      • Green-side Bunker -  ready for drainage installation and then Better Billy Bunker liner installation
      • Waste Bunker along the fairway is 60% complete
    • Hole #18 - Green-side bunkers are being shaped 
  • Grassing:
    • 12 holes are 95% grassed or fully complete.
    • Remaining Order of holes:16, 15, 18, 10, 9, 1, 2 
    • Holes #17
      • All areas have been grassed 
  • Cartpath Installation:
    • Hole #1 & #2 - Complete

    Upcoming Week Goals:
    • Grassing: 
      • Celebration Bermudagrass
        • Complete hole #16
      • TifGrand Bermudagrass
        • Complete holes 15, 18, 10, 9, 1, and 2
      • TifEagle (Greens)
        • Complete holes 15, 18, 10, 9, 1, and 2
    • Bunker Construction:
      • Install drainage and Better Billy Bunker in the green-side bunker on #15
      • Continue Bunker shaping around the #18 Green

    Did you know:

    The large concrete structure located on hole #2 was intended to be used as replacement for the weir structure in the lake on hole #7. Instead the structure that is there was modified and thus the structure on hole #2 is going to be returned.


    Member Course Tours:

    Wednesday, June 24th @ 10:30 AM



    Should you have any question or comments, please feel free to send them to heron@theoaksclub.com or call the Heron Hotline at 966-6940 



    *Please know that the entire Heron Golf Course is a construction zone. To Ensure your safety, please do not access the Heron course at any time. Should you see anyone out walking or driving on the course not accompanied by Management, please notify the Golf Shop or Security.



    Progress Video:

    Click Here to view the Progress Video
    Password = oaks


    The Heron Implementation Team