Week 41 Accomplishments
- Greens:
- Regrading and checking the rootzone depth
- Hole # 15 - Complete
- Bunker Construction:
- Hole #14 - Drainage installation and Better Billy Bunker liner installed in the green-side bunker
- Grassing:
- Order of holes: 3 - 8, 11 - 18, 10, 9, 1, 2
- Order of installation
- Sodding around bunkers / lake banks / drains
- TifGrand Bermudagrass - Collars, Approaches, and Chipping areas
- Celebration Sprigs
- Holes #13
- All areas have been grassed with the exception of the green
Upcoming Week Goals:
- Grassing: Sprig and Sod Holes #12 & #14 except for the greens
- Complete Landscape installation along #3 roadway
- Complete the cartpath installation on hole #1
Did you know:
One of the golf course sprinklers irrigates approximately 3,100 square feet.
Member Course Tours:
Dates and Time:
No tours are scheduled for this coming week
Should you have any question or comments, please feel free to send them to heron@theoaksclub.com or call the Heron Hotline at 966-6940
*Please know that the entire Heron Golf Course is a construction zone. To Ensure your safety, please do not access the Heron course at any time. Should you see anyone out walking or driving on the course not accompanied by Management, please notify the Golf Shop or Security.