- Greens:
- Regrading and checking the rootzone depth:
- Hole #7 - Complete
- Hole #8 - 80% Complete
- Irrigation
- Hole #18 - 100% Complete
- Cartpath Installation
- #11 - 100% complete
- #10 - 90% complete
- Bunker Construction
- Finish shaping:
- Hole #8 - Green-side Bunker is complete
- Better Billy Bunker Liner Installation
- Hole #7 - All bunkers complete
- Hole #8 - Complete
- Better Billy Bunker Liner Information:
- Website: www.billybunker.com
- Grassing
- Order of holes: 3 - 8, 11 - 18, 10, 9, 1, 2
- Order of installation:
- Sodding around bunkers / lake banks / drains
- Sprigging
- Hole #4
- All Areas have been grassed
- Landscape Installation
- Additional Plantings and Irrigation on holes #8, #9, #13, #14, and #18.
- Wetland Area plantings on #14 / #15 have begun.
Upcoming Week Goals:
- Sprig and Sod Celebration on Hole #5
- Sprig and Sod TifGrand on approaches and green collars on holes #6, #7, and #8
- Complete Cartpath Installation on hole #10 Tee, #1 Tee, and #9 Green
- Complete the Better Billy Bunker liner installation on hole #8
- Complete the plantings in the wetland #14 / #15.
- Complete the modification of the weir structure on the lake of #7 and regrade the drainage swale to the correct elevations.
- Greens Grassing is scheduled to begin the week of May 12th.
Golf Course Architect, Jason Straka's next scheduled site visits are:
1) May 7th - May 8th
Did you know:
The first mowing of the sprigged areas will be approximately 4 weeks from the original grassing date..
Member Course Tours:
Dates & Time:
Friday, May 8th @ 9:30
Friday, May 8th @ 9:30
Should you have any questions or comments, please feel free to send them to heron@theoaksclub.com or call the Heron Hotline at 966-6940.
Progress Video:
The Heron Implementation Team