- Greens:
- Regrading and checking the rootzone depth:
- Hole #4 - Complete
- Hole #5 - Complete
- Hole #6 - Complete
- Irrigation
- Hole #18
- Mainline pipe has been installed.
- Sprinklers and Lateral Piping has been installed on tee complex. The areas on the south side of North Creek are currently being installed.
- Cartpath Installation
- #17 - 100% complete
- #2 - 50% complete
- Geotube Installation
- Hole #15 - area around the green side bunker is 100% complete
- Hole #8 - completed the final bag along the green
- GeoTube is 100% complete for the project!
- Bunker Construction
- Finish shaping:
- Hole #7 - All Fairway Bunkers are complete
- Better Billy Bunker Liner Installation
- Hole #6 - All bunkers complete
- Hole #7 - fairway bunker closest to the green
- Better Billy Bunker Liner Information:
- Website: www.billybunker.com
- Grassing
- Order of holes: 3 - 8, 11 - 18, 10, 9, 1, 2
- Order of installation:
- Sodding around bunkers / lake banks / drains
- Sprigging
- Hole #3
- Sod is has been laid around all the bunker complexes and lake bank with the Geotube and miscellaneous areas that have a high potential for erosion during a rain event
- TifGrand Bermudagrass sod and sprigs have installed around the entire green complex.
- Celebration sprigs are currently being installed from the bridge to the green.
- Hole #4
- Sod has been laid along the lake banks and bunker edges.
- TifGrand Bermudagrass sod and sprigs has been installed around the entire green complex.
- Fumigation of Tees:
- All plastic tarps have been removed from the tees that were fumigated.
- The remaining tees (#1, #10, #14, #15, #18) are scheduled to be fumigated on May 4th.
Upcoming Week Goals:
- Sprig Celebration on Hole #4
- Complete Cartpath Installation on hole #11 and start #10
- Complete the installation of Irrigation piping and sprinklers on hole #18
- Complete the Better Billy Bunker liner installation on hole #7 and #8
- Complete the modification of the weir structure on the lake of #7 and regrade the drainage swale to the correct elevations.
- Greens Grassing is scheduled to begin the week of May 12th.
Golf Course Architect, Jason Straka's next scheduled site visits are:
1) April 29th - May 1st
Did you know:
Irrigation Information:
The new sprinklers have the capability of dispersing approximately 80 gallons of water per minute. Each station is controlled individually by a computer locating in the Green and Grounds Maintenance building.
Member Course Tours:
Dates & Time:
Friday, May 1st @ 1:30
Friday, May 1st @ 1:30
Should you have any questions or comments, please feel free to send them to heron@theoaksclub.com or call the Heron Hotline at 966-6940.
Progress Video:
Password: "oaks"
The Heron Implementation Team