Friday, April 3, 2015

Progress Update #31 - Week 33 - 4/3/2015


Week 33 Accomplishments:
  • Irrigation
    • The  main line, lateral piping, sprinkler installation:  
      • Hole #1 - 35% complete
  • Cartpath Installation 
      • #12 - 100% Complete
      • #13 - 100% Complete
      • #14 - 85% Complete    
  • Geotube Installation
    • Hole #1 
      • Left side of fairway - 90% complete
      • working on the right side of the fairway to the green
  • Weir Structure Replacement 
    • Weir - structures that control the water elevations in the lake
    • Completed on:
      • Hole #12
      • Hole #15
      • Hole #16
      • Remaining Structures to be replaced:
        • Hole #7
  • Bunker Construction
    • Finish shaping:
      • Hole #3 - All bunkers
      • Hole #4 - Back right bunker
      • Hole #5 - All Bunkers 
      • Hole #6 - Fairway Bunker
    • Better Billy Bunker Liner Installation

Upcoming Week Goals:
  • Complete the Cartpath Installation on hole #14 and start #15
  • Complete the Irrigation installation on hole #1
  • Complete the Better Billy Bunker liner installation on hole #3 and #4
  • Continue to flush and pressurize the Irrigation System
  • Geotube Installation - complete the right side of the fairway
  • Modify the current weir structure on the lake of #7 and regrade the drainage swale to the correct elevations.
  • Fumigation of Tees
    • Purpose: Eradicate any Nematode population that may still be viable.
    • Product used: Basamid 
    • Licensed Applicators: TriEst Ag Group Inc.
    • Timeframe of Application:
      • 1st Application: 
        • Date: April 8th (1 day)
        • Holes: 2 - 8, 11 - 13
        • Tarps perforated: April 13th (Monday)
        • Tarps removed: April 14th (Tuesday) 
      • 2nd Application: 
        • Date: Tentatively scheduled week of April 20th
        • Holes: 1, 9, 10, 14 - 18
    • Application information:
      • Once the product is applied to the ground it's then watered in until the soil reaches a specific moisture level. 
      • Following the watering process a plastic tarp is then laid over top of the application area for a 5 day period. Once the tarps of have been on the ground for a total of a 120 hours the applicators then perforate the tarps and leave them sit for an additional 24 hours. 
    • Buffer Zones and Re-entry Period: 
      • There are strict rules regarding buffer zones with is a 30 foot distance from structures and bodies of water.
      • Outside the drip line of trees.
      • Once the product is applied there is a re-entry interval of 48 hours. Anyone who is to enter any of the treated areas during this period is required to have the correct personal protective equipment.
    • Posting Signage in treated areas
      • Each area will have specific signage signifying that the area has been treated.

The Look Ahead:
  • Grass Installation:  Grass installation will begin the week of April 6th.
  • The projected opening date is early November.

Golf Course Architect, Jason Straka's next scheduled site visits are:   

1) April 8th - 10th 

2) April 15th - 17th




Did you know:  

Greens will be firm upon opening due to a lack of maturity.  Greens develop a mat layer, akin to carpet padding.  This is what holds well-struck golf shots.  It takes approximately two to three years for this mat layer to fully develop.


Member Course Tours: 

Dates & Time:

1) April 9th @ 2:30 pm




Should you have any questions or comments, please feel free to send them to heron@theoaksclub.com or call the Heron Hotline at 966-6940.



*Please know that the entire Heron Golf Course is a construction zone.  To ensure your safety, please do not access the Heron course at any time

Progress Video:

Password: "oaks"



The Heron Implementation Team