- Irrigation
- The main line, lateral piping, sprinkler installation:
- Hole #1 - 100% complete
- The design is laid out on hole #18
- Cartpath Installation
- #14 - 100% Complete
- #15 - 95% Complete (Access points left open)
- #16 - 95% complete
- Geotube Installation
- Hole #1
- Left side of fairway - 100% complete
- Right side of the fairway to the green - 75% complete
- Weir Structure Replacement
- Weir - structures that control the water elevations in the lake
- Remaining Structure currently being modified:
- Hole #7
- Bunker Construction
- Finish shaping:
- Hole #4 - All bunkers
- Hole #6 - All bunkers
- Better Billy Bunker Liner Installation
- Hole #3 - complete
- Better Billy Bunker Liner Information:
- Website: www.billybunker.com
- Grassing
- Hole #3
- Sod is being laid around the fairway bunker complex and lake bank
- Landscape
- Hole #1 - Bougainvillea have been planted behind the green. Landscape irrigation has been installed in this bed.
- Hole #3 - Native grasses planted behind left fairway bunker
- Hole #4 - Native grasses planted behind the back left bunker. Landscape irrigation has been installed in this bed.
- Hole #5 - Native grasses planted behind the green-side bunker
- Hole #8 -
- Clusia, Bougainvillea, and native grasses planted behind the tees / roadside. Landscape irrigation has been installed in this bed.
- Calypso Oleanders and Petite Pink Oleanders have been installed behind the green
- Hole #9 -
- Clusia and Bougainvillea have been planted behind the tee / along the roadside. Landscape irrigation has been installed in this bed.
- Landscape irrigation has been installed to all the large plant material behind the green.
- Hole #13 - Shady Lady Olive trees have been planted on the berm behind the green.
Upcoming Week Goals:
- Continue the grassing on holes #3 and #4
- Float / Check green rootzone depth and mix on holes #3 and #4
- Complete the Cartpath Installation on hole #17
- Continue to flush irrigation system and setup the satellite box station sequences
- Complete the Better Billy Bunker liner installation on hole #4 & 5
- Complete the modification of the weir structure on the lake of #7 and regrade the drainage swale to the correct elevations.
- Fumigation of Tees
- Purpose: Eradicate any Nematode population that may still be viable.
- Product used: Basamid
- Licensed Applicators: TriEst Ag Group Inc.
- Timeframe of Application:
- 1st Application:
- Date: April 13th (1 day)
- Holes: 2 - 9, 11 - 13
- Tarps perforated: April 20th (Monday)
- Tarps removed: April 21st (Tuesday)
- 2nd Application:
- Date: Tentatively scheduled week of April 20th
- Holes: 1, 10, 14 - 18
- Application information:
- Once the product is applied to the ground it's then watered in until the soil reaches a specific moisture level.
- Following the watering process a plastic tarp is then laid over top of the application area for a 5 day period. Once the tarps of have been on the ground for a total of a 120 hours the applicators then perforate the tarps and leave them sit for an additional 24 hours.
- Buffer Zones and Re-entry Period:
- There are strict rules regarding buffer zones with is a 30 foot distance from structures and bodies of water.
- Outside the drip line of trees.
- Once the product is applied there is a re-entry interval of 48 hours. Anyone who is to enter any of the treated areas during this period is required to have the correct personal protective equipment.
- Posting Signage in treated areas
- Each area will have specific signage signifying that the area has been treated.
Golf Course Architect, Jason Straka's next scheduled site visits are:
1) April 15th - 17th
Did you know:
Grassing Information:
Sprigging is the process of removing stems (stolons
or rhizomes) from mature bermudagrass stands and
replanting the vegetative cuttings in a different location.
Any grass that has a lateral growth habit can be established
by sprigs, but the aggressive growth rate of bermudagrass
makes sprigging a very popular way of establishing new
fields. Sprigs are typically from 3 to 5 inches long and
contain numerous nodes (i.e. growing points) from which
new roots and shoots develop.
Member Course Tours:
Dates & Time:
1) April 16th @ 2:30 pm
1) April 16th @ 2:30 pm
Should you have any questions or comments, please feel free to send them to heron@theoaksclub.com or call the Heron Hotline at 966-6940.
Progress Video:
Password: "oaks"
The Heron Implementation Team