Progress Update #49 - Week 51 - 8/7/15


Week 51 Accomplishments 

  • Grassing:
    • Hole #1 - 95% complete
    • Hole #9 - 100% complete
    • Hole #2 - Sod has been laid around the tee complex and continues around the bunkers
  • Bunker Construction:
    • Hole #1 - 100% complete
    • Hole #2 - 90% complete (sand installation will be completed on Saturday, August 8th)

Upcoming Week Goals:
  • Grassing: 
    • Hole #2 - complete the remaining grass installation by Wednesday, August 12th.
  • Southeastern Golf will begin the punch-list that has been created by Jason Straka (Course Architect) and Joe Voss (Project Manager).


Did you know:

A year ago the 2nd grass eradication application was being applied to the course.


Member Course Tours:

Wednesday, August 12th @ 1:30 PM


Should you have any question or comments, please feel free to send them to heron@theoaksclub.com or call the Heron Hotline at 966-6940 



*Please know that the entire Heron Golf Course is a construction zone. To Ensure your safety, please do not access the Heron course at any time. Should you see anyone out walking or driving on the course not accompanied by Management, please notify the Golf Shop or Security.



Progress Video:

Click Here to view the Week #50 Progress



The Heron Implementation Team