Saturday, September 27, 2014

Progress Update #7 - Week 6 - 9/26/2014





Week 6 Accomplishments:
  • Greens Complexes
    • Hole #7 Greens contours have been approved by Jason Straka
    • Hole #2 Complex has been rough shaped and will be ready for Jason's approval during his next site visit.
  • Earthmoving / Shaping
    • Work continues on holes 5, 6, 7 and has begun on #2
    • The de-watering and excavation of the pond surrounding #5 green has begun.
    • Excavating soil continues on #5 fairway which is being relocated to #7 fairway.  
  • Drainage installation
    • Greens Installations - #3 Green is complete. #6 Green has begun
    • General Course Drainage - #3 is complete. #6 has begun and will continue this coming week
  • Clearing Plan 
    • Work continued on holes 5 and 7. Hole #6 is complete and work has begun on #2.
    • The Cartpath at the tee on #3 is being removed and majority of the concrete from holes 3 - 7 has been hauled off site to a recycling location.

Upcoming Week Goals:
  • Continue shaping #2 Greens Complex and have the green contours ready for Jason's approval during his next site visit.
  • Continue Earthmoving and Rough Shaping on holes 2, 5, 7 and the Greens complex of hole #1
  • Drainage Installation
    • Continue on hole #6 and proceed to #7.
    • Complete Greens drainage on #6 and start #7.
  • Continue Clearing Plan on hole #2 and #8.
  • Rototilling on holes #1 and #2

The Look Ahead:
  • Geotube Installation:
    • Scheduled to begin the week of October 6th
    • #4 greens complex pond bank, #3 tee complex pond bank, and #2 tee water canal bank will be the areas they will start.
  • In the next 2 - 3 weeks the contractor will begin rototilling and the earthwork phase on holes 13 - 15. 
  • Irrigation Installation:
    • Hole #3 will be the first area for the installation.
    • Scheduled to begin in the next 2 - 3 weeks. 

Golf Course Architect next scheduled site visit: 
Tuesday, September 30th - Wednesday, October 1st. 



Did you know:  

Over 48,000 linear feet or 9 miles of silt fence has been installed around the course.


Progressive Journal Access
  • Please note the Progressive Journal can also be accessed through the Club's website. Past Journal posting are archived at this location. 

Progress Video:





Should you have any questions or comments, please feel free to send them to heron@theoaksclub.com or call the Heron Hotline at 966-6940.

*Please know that the entire Heron Golf Course is a construction zone.  To ensure your safety, please do not access the Heron course at any time*



The Heron Implementation Team