Week 6 Accomplishments:
- Greens Complexes
- Hole #7 Greens contours have been approved by Jason Straka
- Hole #2 Complex has been rough shaped and will be ready for Jason's approval during his next site visit.
- Earthmoving / Shaping
- Work continues on holes 5, 6, 7 and has begun on #2
- The de-watering and excavation of the pond surrounding #5 green has begun.
- Excavating soil continues on #5 fairway which is being relocated to #7 fairway.
- Drainage installation
- Greens Installations - #3 Green is complete. #6 Green has begun
- General Course Drainage - #3 is complete. #6 has begun and will continue this coming week
- Clearing Plan
- Work continued on holes 5 and 7. Hole #6 is complete and work has begun on #2.
- The Cartpath at the tee on #3 is being removed and majority of the concrete from holes 3 - 7 has been hauled off site to a recycling location.
Upcoming Week Goals:
- Continue shaping #2 Greens Complex and have the green contours ready for Jason's approval during his next site visit.
- Continue Earthmoving and Rough Shaping on holes 2, 5, 7 and the Greens complex of hole #1
- Drainage Installation
- Continue on hole #6 and proceed to #7.
- Complete Greens drainage on #6 and start #7.
- Continue Clearing Plan on hole #2 and #8.
- Rototilling on holes #1 and #2
The Look Ahead:
- Geotube Installation:
- Scheduled to begin the week of October 6th
- #4 greens complex pond bank, #3 tee complex pond bank, and #2 tee water canal bank will be the areas they will start.
- In the next 2 - 3 weeks the contractor will begin rototilling and the earthwork phase on holes 13 - 15.
- Irrigation Installation:
- Hole #3 will be the first area for the installation.
- Scheduled to begin in the next 2 - 3 weeks.
Golf Course Architect next scheduled site visit:
Tuesday, September 30th - Wednesday, October 1st.
Did you know:
Over 48,000 linear feet or 9 miles of silt fence has been installed around the course.
Progressive Journal Access:
- Please note the Progressive Journal can also be accessed through the Club's website. Past Journal posting are archived at this location.
- The Oaks Club Website - Click Here
- Golf / Grounds
- Heron Renovation Project
- Heron Progressive Journal
Progress Video:
*Please know that the entire Heron Golf Course is a construction zone. To ensure your safety, please do not access the Heron course at any time*
The Heron Implementation Team