Week 7 Accomplishments:
- Greens Complexes
- Hole #2 Greens contours are close to being approved and will be ready for approvel during Jason Straka's next site visit.
- Earthmoving / Shaping
- Work continues on holes #6, #7, #2 and has begun on #1
- The de-watering and excavation of the pond surrounding #5 green will continue for the next 5 - 7 days.
- Drainage installation
- General Course Drainage - #3 and #6 is complete. #7 will start on Friday (10/3) and will continue over the next 7 days. The property boundaries will be the main focus while rough shaping continues on the fairway areas.
- Clearing Plan
- Hole #2 is complete and work has started on #8
- The Cartpath at the tee on #3, #2, #8, and the path around #1 green have been removed.
Upcoming Week Goals:
- Greens Contours on #2 and #1 to be ready for Jason's approval
- Continue Earthmoving and Rough Shaping on holes #2, #5, #7, #8 and the Greens complex of hole #1.
- Drainage Installation
- Hole #7 Property Boundaries will be the main focus which will occur prior to shaping the entire golf hole.
- Complete Greens drainage on #7 and start #2 following the contour approval.
- Continue Clearing Plan on hole #8 and proceed to #1 and #9.
The Look Ahead:
- Geotube Installation:
- Scheduled to begin the week of October 13th
- #4 greens complex pond bank, left side of #3 tee complex pond bank, and #2 tee water canal bank will be the areas they will start.
- In the next 1-2 weeks the contractor will begin rototilling and the earthwork phase on holes #13 - #15.
Golf Course Architect next scheduled site visit:
Wednesday, October 8th
Did you know:
There will be over 16,000 linear feet or 3 miles of 6 inch ADS N-12 Drainage Pipe installed on the course.
Progressive Journal Access:
- Please note the Progressive Journal can also be accessed through the Club's website. Past Journal posting are archived at this location.
- The Oaks Club Website - Click Here
- Golf / Grounds
- Heron Renovation Project
- Heron Progressive Journal
Progress Video:
*Please know that the entire Heron Golf Course is a construction zone. To ensure your safety, please do not access the Heron course at any time*
The Heron Implementation Team