Week 8 Accomplishments:
- Greens
- Contours on holes #1 and #2 have been approved by Jason Straka.
- Drainage and gravel installation is complete on #2.
- Earthmoving / Shaping
- Work continues on holes #7, #2, #1 and has begun on #8. The greens complex on #8 is dropping by 1 - 2 feet and the earth from this area is being utilized to create a berm between the green area and MacEwen road.
- The de-watering and excavation of the pond surrounding #5 green is now over half way complete. Anticipated to be complete in the next 3 - 4 days.
- Roto-tilling has begun on hole #11 and #12.
- Drainage installation
- General Course Drainage - The tee area on #7 is complete. Work will continue down both property lines of the hole over the next 2 - 3 days.
- Clearing Plan
- Hole #8 is nearly complete and will be complete in the next day or two.
- The cartpath at the tee on #9 and the greens complex on #1 have been removed.
Upcoming Week Goals:
- Rough shape the green on #5.
- Complete the drainage and gravel installation on hole #1.
- Continue Earthmoving and Rough Shaping on hole #8.
- Start Earthmoving and Shaping on holes #11 & #12
- Drainage Installation:
- Start hole #2 fairway drainage.
- Continue Clearing Plan on hole #8 and proceed to #11 and #12.
The Look Ahead:
- Geotube Installation:
- Scheduled to start today (Friday, 10/10/14)
- This process will begin on #4 greens complex pond bank
- Irrigation Installation will start in the few weeks.
Golf Course Architect next scheduled site visit:
Wednesday, October 15th - Friday, October 17th
Did you know:
There will be 15,400 linear feet or 2.94 miles of 8 inch HDPE Irrigation Pipe installed on the course.
Progressive Journal Access:
- Please note the Progressive Journal can also be accessed through the Club's website. Past Journal posting are archived at this location.
- The Oaks Club Website - Click Here
- Golf / Grounds
- Heron Renovation Project
- Heron Progressive Journal
Progress Video:
*Please know that the entire Heron Golf Course is a construction zone. To ensure your safety, please do not access the Heron course at any time*
The Heron Implementation Team