Week 3 Accomplishments:
- Greens
- Soil is being removed and stockpiled for tees
- Existing soil has been excavated on holes 2 - 8
- Erosion Control
- Silt Fence Installation - Completed on Holes 1-12
- Turbidity Barrier Installation - Installed in #3 Lake & #4 Lake
- Earthmoving / Shaping
- Continue to work on holes #3 and #4
- Existing Irrigation Removal
- Completed on holes 1-9
- Pepper Tree Removal on #14/15 Wetland area has begun
- Clearing Plan
- Completed on holes 3 - 5
Upcoming Week Goals:
- Complete Silt Fence Installation on entire holes 10 - 18
- Greens soil removal: 10 - 15
- Complete irrigation head extraction on hole 10-18
- Continue to install tree protection fencing
- Earthmoving / shaping on holes 3 - 6
- Clearing Plan 6 - 8
Click here for the progress video
Should you have any questions or comments, please feel free to send them to heron@theoaksclub.com or call the Heron Hotline at 966-6940.
Please remember the entire golf course is a construction zone. To ensure your safety, we kindly request that you not access the course unless approved by a Implementation Team Member.
The Heron Implementation Team