Friday, September 5, 2014

Progress Update #4 - Week 3 - 9/5/2014




Week 3 Accomplishments:
  • Greens 
    • Soil is being removed and stockpiled for tees
    • Existing soil has been excavated on holes 2 - 8
  • Erosion Control
    • Silt Fence Installation - Completed on Holes 1-12
    • Turbidity Barrier Installation - Installed in #3 Lake & #4 Lake
  • Earthmoving / Shaping
    • Continue to work on holes #3 and #4
  • Existing Irrigation Removal
    • Completed on holes 1-9
  • Pepper Tree Removal on #14/15 Wetland area has begun
  • Clearing Plan 
    • Completed on holes 3 - 5


Upcoming Week Goals:
  • Complete Silt Fence Installation on entire holes 10 - 18
  • Greens soil removal: 10 - 15
  • Complete irrigation head extraction on hole 10-18
  • Continue to install tree protection fencing
  • Earthmoving / shaping on holes 3 - 6
  • Clearing Plan 6 - 8

Please click on the below link to view a progress update video:

Click here for the progress video


Should you have any questions or comments, please feel free to send them to heron@theoaksclub.com or call the Heron Hotline at 966-6940.

Please remember the entire golf course is a construction zone. To ensure your safety, we kindly request that you not access the course unless approved by a Implementation Team Member.


The Heron Implementation Team