Progress Update #36 - Week 38 - 5/8/2015


Week 38 Accomplishments:
  • Greens:
    • Regrading and checking the rootzone depth:
      • Hole #8 - Complete
  • Irrigation
    • All the main irrigation is complete. There are still roadway zones to be installed on holes #2 and #3.
  • Cartpath Installation 
    • #10 - 100% Complete 
    • #1 / #9 - Complete to / from the bridge
    • #7 - 100% Complete 
    • Bunker Construction
      • Finish shaping:
        • Holes #11, #12, and #13 are complete
        • Grassing
          • Order of holes: 3 - 8, 11 - 18, 10, 9, 1, 2
          • Order of installation: 
            • Sodding around bunkers / lake banks / drains
            • Sprigging 
          • Hole #5
            • All Areas have been grassed
        • Landscape Installation
          • Mulching continues on the beds currently planted to 90 - 100%
          • Wetland Area plantings on #14 / #15.

        Upcoming Week Goals:
        • Sprig Celebration on holes #6 and #7 
        • Complete the Better Billy Bunker liner installation on hole #11
        • Greens Grassing is scheduled to the week of May 18th on holes # 3 - #8



          A look ahead:
          • Grassing Projected Schedule:
            • Week of May 11th
              • Complete all grassing on holes #6 & #7
            • Week of May 18th
              • Complete all grassing on hole #8
              • Complete greens grassing on holes #3 - #8
              • Complete TifGrand Bermudagrass installation on holes #11, #12, and #13
            • Week of May 25th 
              • Complete all grassing on holes #12 & #13




          Golf Course Architect, Jason Straka's next scheduled site visits are:   

          1) May 18th - May 20th

          2) May 27th - May 28th
          *Jason will not be onsite next week due to a business trip to Singapore 





          Did you know:  
           The aquatic plants installed in the renovated wetland on holes #14 and #15 include Pickerelweed, Arrowhead, Bulrush, and Giant Leather Fern on the islands.

          Bulrush will also be planted around select weir structures to block the view. 


            Member Course Tours: 

            Dates & Time:

            Monday, May 18th @ 2:30




            Should you have any questions or comments, please feel free to send them to heron@theoaksclub.com or call the Heron Hotline at 966-6940.



            *Please know that the entire Heron Golf Course is a construction zone.  To ensure your safety, please do not access the Heron course at any time



            Progress Video:





            The Heron Implementation Team

            Friday, May 1, 2015

            Progress Update #35 - Week #37 - 5/1/2015


            Week 37 Accomplishments:
            • Greens:
              • Regrading and checking the rootzone depth:
                • Hole #7 - Complete
                • Hole #8 - 80% Complete
            • Irrigation
              • Hole #18 - 100% Complete
            • Cartpath Installation 
              • #11 - 100% complete 
              • #10 - 90% complete  
              • Bunker Construction
                • Finish shaping:
                  • Hole #8 - Green-side Bunker is complete
                • Better Billy Bunker Liner Installation
                  • Hole #7 - All bunkers complete
                  • Hole #8 - Complete
                  • Better Billy Bunker Liner Information:
                • Grassing
                  • Order of holes: 3 - 8, 11 - 18, 10, 9, 1, 2
                  • Order of installation: 
                    • Sodding around bunkers / lake banks / drains
                    • Sprigging 
                  • Hole #4
                    • All Areas have been grassed
                • Landscape Installation
                  • Additional Plantings and Irrigation on holes #8, #9, #13, #14, and #18. 
                  • Wetland Area plantings on #14 / #15 have begun.

                Upcoming Week Goals:
                • Sprig and Sod Celebration on Hole #5
                • Sprig and Sod TifGrand on approaches and green collars on holes #6, #7, and #8
                • Complete Cartpath Installation on hole #10 Tee, #1 Tee, and #9 Green
                • Complete the Better Billy Bunker liner installation on hole #8
                • Complete the plantings in the wetland #14 / #15.
                • Complete the modification of the weir structure on the lake of #7 and regrade the drainage swale to the correct elevations.
                • Greens Grassing is scheduled to begin the week of May 12th.


                  Golf Course Architect, Jason Straka's next scheduled site visits are:   

                  1) May 7th - May 8th




                  Did you know:  
                  The first mowing of the sprigged areas will be approximately 4 weeks from the original grassing date..  

                    Member Course Tours: 

                    Dates & Time:

                    Friday, May 8th @ 9:30




                    Should you have any questions or comments, please feel free to send them to heron@theoaksclub.com or call the Heron Hotline at 966-6940.



                    *Please know that the entire Heron Golf Course is a construction zone.  To ensure your safety, please do not access the Heron course at any time

                    Progress Video:





                    The Heron Implementation Team

                    Friday, April 24, 2015

                    Progress Update #34 - Week 36 - 4/24/2015


                    Week 36 Accomplishments:
                    • Greens:
                      • Regrading and checking the rootzone depth:
                        • Hole #4 - Complete
                        • Hole #5 - Complete
                        • Hole #6 - Complete
                    • Irrigation
                      • Hole #18
                        • Mainline pipe has been installed.
                        • Sprinklers and Lateral Piping has been installed on tee complex. The areas on the south side of North Creek are currently being installed.
                    • Cartpath Installation 
                      • #17 - 100% complete 
                      • #2 - 50% complete  
                    • Geotube Installation
                      • Hole #15 - area around the green side bunker is 100% complete
                      • Hole #8 - completed the final bag along the green
                      • GeoTube is 100% complete for the project!
                      • Bunker Construction
                        • Finish shaping:
                          • Hole #7 - All Fairway Bunkers are complete
                        • Better Billy Bunker Liner Installation
                          • Hole #6 - All bunkers complete
                          • Hole #7 - fairway bunker closest to the green
                          • Better Billy Bunker Liner Information:
                      • Grassing
                        • Order of holes: 3 - 8, 11 - 18, 10, 9, 1, 2
                        • Order of installation: 
                          • Sodding around bunkers / lake banks / drains
                          • Sprigging 
                        • Hole #3 
                          • Sod is has been laid around all the bunker complexes and lake bank with the Geotube and miscellaneous areas that have a high potential for erosion during a rain event 
                          • TifGrand Bermudagrass sod and sprigs have installed around the entire green complex.
                          • Celebration sprigs are currently being installed from the bridge to the green.
                        • Hole #4
                          • Sod has been laid along the lake banks and bunker edges.
                          • TifGrand Bermudagrass sod and sprigs has been installed around the entire green complex.
                      • Fumigation of Tees:
                        • All plastic tarps have been removed from the tees that were fumigated.
                        • The remaining tees (#1, #10, #14, #15, #18) are scheduled to be fumigated on May 4th.

                      Upcoming Week Goals:
                      • Sprig Celebration on Hole #4
                      • Complete Cartpath Installation on hole #11 and start #10
                      • Complete the installation of Irrigation piping and sprinklers on hole #18
                      • Complete the Better Billy Bunker liner installation on hole #7 and #8
                      • Complete the modification of the weir structure on the lake of #7 and regrade the drainage swale to the correct elevations.
                      • Greens Grassing is scheduled to begin the week of May 12th.


                      Golf Course Architect, Jason Straka's next scheduled site visits are:   

                      1) April 29th -  May 1st




                      Did you know:  

                      Irrigation Information:
                      The new sprinklers have the capability of dispersing approximately 80 gallons of water per minute. Each station is controlled individually by a computer locating in the Green and Grounds Maintenance building.

                        Member Course Tours: 

                        Dates & Time:

                        Friday, May 1st @ 1:30




                        Should you have any questions or comments, please feel free to send them to heron@theoaksclub.com or call the Heron Hotline at 966-6940.



                        *Please know that the entire Heron Golf Course is a construction zone.  To ensure your safety, please do not access the Heron course at any time

                        Progress Video:

                        Password: "oaks"



                        The Heron Implementation Team

                        Thursday, April 16, 2015

                        Progress Update #33 - Week 35 - 4/17/2015


                        Week 35 Accomplishments:
                        • Greens:
                          • Regrading and checking the rootzone depth:
                            • Hole #3 - Complete
                            • Hole #4 - 80% complete
                        • Irrigation
                          • Hole #18 - the mainline pipe has been fused and is currently being installed.
                        • Cartpath Installation 
                          • #16 - 100% complete 
                          • #17 - 95 % complete   
                        • Geotube Installation
                          • Hole #1 
                            • Right side of the fairway to the green - 100% complete
                        • Bunker Construction
                          • Finish shaping:
                            • Hole #7 - All Fairway Bunkers are complete
                          • Better Billy Bunker Liner Installation
                            • Hole #4 - complete
                            • Hole #5 - complete
                            • Hole #6 - Fairway bunker complete
                            • Better Billy Bunker Liner Information:
                          • Sand Installation (G-Angle)
                            • Holes #3 & #4
                        • Grassing
                          • Hole #3 
                            • Sod is has been laid around all the bunker complexes and lake bank with the Geotube.
                            • The entire hole is currently being finished shaped in preparation for sprigging which is schedule to start next Wednesday (April 22nd).
                          • Hole #4
                            • Sod is being laid along the lake banks and bunker edges and the around entire right front green-side bunker complex.
                        • Landscape
                          • Hole #4
                            • Purple Bougainvillea have been plant around the Bismarck Palms. 
                          • Hole #8 
                            • Landscape Irrigation has been installed in the bed behind the green
                          • Hole #9 
                            • Calypso Oleanders have been planted under and around the Sabal palms behind the green-side bunkers.
                        • Fumigation of Tees:
                          • Product Applied on holes 2, 3, 4, 5, 6, 7, 8, 9, 11, 12, 13, 16, 17
                          • The plastic tarps will be perforated on holes 2 - 9 on Sunday for a Monday removal of the tarps. The tarps on holes 11, 12, 13, 16, & 17 will be perforated on Monday with a Tuesday removal.

                        Upcoming Week Goals:
                        • Sprig Celebration on Hole #3
                        • Complete the Cartpath Installation on hole #17
                        • Install the Irrigation piping and sprinklers on hole #18
                        • Complete the Better Billy Bunker liner installation on hole #6
                        • Complete the modification of the weir structure on the lake of #7 and regrade the drainage swale to the correct elevations.
                        • Fumigation of Tees
                          • Purpose: Eradicate any Nematode population that may still be viable.
                          • Product used: Basamid 
                          • Licensed Applicators: TriEst Ag Group Inc.
                          • Timeframe of Application:
                            • 2nd Application: 
                              • Date: Monday, May 4th
                              • Holes: 1, 10, 14, 15, 18
                          • Application information:
                            • Once the product is applied to the ground it's then watered in until the soil reaches a specific moisture level. 
                            • Following the watering process a plastic tarp is then laid over top of the application area for a 5 day period. Once the tarps of have been on the ground for a total of a 120 hours the applicators then perforate the tarps and leave them sit for an additional 24 hours. 
                          • Buffer Zones and Re-entry Period: 
                            • There are strict rules regarding buffer zones with is a 30 foot distance from structures and bodies of water.
                            • Outside the drip line of trees.
                            • Once the product is applied there is a re-entry interval of 48 hours. Anyone who is to enter any of the treated areas during this period is required to have the correct personal protective equipment.
                          • Posting Signage in treated areas
                            • Each area will have specific signage signifying that the area has been treated.


                        Golf Course Architect, Jason Straka's next scheduled site visits are:   

                        1) April 22nd - 24th




                        Did you know:  

                        Grassing Information:
                        Following the application / installation of sprigs, it is extremely important to keep the sprigs moist. The irrigation system will run on a continuous basis through-out the day to ensure the sprigs do not dry out.

                          Member Course Tours: 

                          Dates & Time:

                          Wednesday, April 22nd @ 2:30




                          Should you have any questions or comments, please feel free to send them to heron@theoaksclub.com or call the Heron Hotline at 966-6940.



                          *Please know that the entire Heron Golf Course is a construction zone.  To ensure your safety, please do not access the Heron course at any time

                          Progress Video:

                          Password: "oaks"



                          The Heron Implementation Team

                          Friday, April 10, 2015

                          Progress Update #32 - Week 34 - 4/10/2015


                          Week 34 Accomplishments:
                          • Irrigation
                            • The  main line, lateral piping, sprinkler installation:  
                              • Hole #1 - 100% complete
                            • The design is laid out on hole #18
                          • Cartpath Installation 
                            • #14 - 100% Complete
                            • #15 - 95% Complete (Access points left open)
                            • #16 - 95% complete    
                          • Geotube Installation
                            • Hole #1 
                              • Left side of fairway - 100% complete
                              • Right side of the fairway to the green - 75% complete
                          • Weir Structure Replacement 
                            • Weir - structures that control the water elevations in the lake
                              • Remaining Structure currently being modified:
                                • Hole #7
                          • Bunker Construction
                            • Finish shaping:
                              • Hole #4 - All bunkers
                              • Hole #6 - All bunkers
                            • Better Billy Bunker Liner Installation
                          • Grassing
                            • Hole #3 
                              • Sod is being laid around the fairway bunker complex and lake bank
                          • Landscape
                            • Hole #1 - Bougainvillea have been planted behind the green. Landscape irrigation has been installed in this bed.
                            • Hole #3 - Native grasses planted behind left fairway bunker
                            • Hole #4 - Native grasses planted behind the back left bunker. Landscape irrigation has been installed in this bed.
                            • Hole #5 - Native grasses planted behind the green-side bunker
                            • Hole #8 - 
                              • Clusia, Bougainvillea, and native grasses planted behind the tees / roadside. Landscape irrigation has been installed in this bed.
                              • Calypso Oleanders and Petite Pink Oleanders have been installed behind the green
                            • Hole #9 - 
                              • Clusia and Bougainvillea have been planted behind the tee / along the roadside. Landscape irrigation has been installed in this bed.
                              • Landscape irrigation has been installed to all the large plant material behind the green.
                            • Hole #13 - Shady Lady Olive trees have been planted on the berm behind the green.

                          Upcoming Week Goals:
                          • Continue the grassing on holes #3 and #4
                          • Float / Check green rootzone depth and mix on holes #3 and #4
                          • Complete the Cartpath Installation on hole #17
                          • Continue to flush irrigation system and setup the satellite box station sequences
                          • Complete the Better Billy Bunker liner installation on hole #4 & 5
                          • Complete the modification of the weir structure on the lake of #7 and regrade the drainage swale to the correct elevations.
                          • Fumigation of Tees
                            • Purpose: Eradicate any Nematode population that may still be viable.
                            • Product used: Basamid 
                            • Licensed Applicators: TriEst Ag Group Inc.
                            • Timeframe of Application:
                              • 1st Application: 
                                • Date: April 13th (1 day)
                                • Holes: 2 - 9, 11 - 13
                                • Tarps perforated: April 20th (Monday)
                                • Tarps removed: April 21st (Tuesday) 
                              • 2nd Application: 
                                • Date: Tentatively scheduled week of April 20th
                                • Holes: 1, 10, 14 - 18
                            • Application information:
                              • Once the product is applied to the ground it's then watered in until the soil reaches a specific moisture level. 
                              • Following the watering process a plastic tarp is then laid over top of the application area for a 5 day period. Once the tarps of have been on the ground for a total of a 120 hours the applicators then perforate the tarps and leave them sit for an additional 24 hours. 
                            • Buffer Zones and Re-entry Period: 
                              • There are strict rules regarding buffer zones with is a 30 foot distance from structures and bodies of water.
                              • Outside the drip line of trees.
                              • Once the product is applied there is a re-entry interval of 48 hours. Anyone who is to enter any of the treated areas during this period is required to have the correct personal protective equipment.
                            • Posting Signage in treated areas
                              • Each area will have specific signage signifying that the area has been treated.


                          Golf Course Architect, Jason Straka's next scheduled site visits are:   

                          1) April 15th - 17th




                          Did you know:  

                          Grassing Information:
                          Sprigging is the process of removing stems (stolons or rhizomes) from mature bermudagrass stands and replanting the vegetative cuttings in a different location. Any grass that has a lateral growth habit can be established by sprigs, but the aggressive growth rate of bermudagrass makes sprigging a very popular way of establishing new fields. Sprigs are typically from 3 to 5 inches long and contain numerous nodes (i.e. growing points) from which new roots and shoots develop. 

                            Member Course Tours: 

                            Dates & Time:

                            1) April 16th @ 2:30 pm




                            Should you have any questions or comments, please feel free to send them to heron@theoaksclub.com or call the Heron Hotline at 966-6940.



                            *Please know that the entire Heron Golf Course is a construction zone.  To ensure your safety, please do not access the Heron course at any time

                            Progress Video:

                            Password: "oaks"



                            The Heron Implementation Team

                            Friday, April 3, 2015

                            Progress Update #31 - Week 33 - 4/3/2015


                            Week 33 Accomplishments:
                            • Irrigation
                              • The  main line, lateral piping, sprinkler installation:  
                                • Hole #1 - 35% complete
                            • Cartpath Installation 
                                • #12 - 100% Complete
                                • #13 - 100% Complete
                                • #14 - 85% Complete    
                            • Geotube Installation
                              • Hole #1 
                                • Left side of fairway - 90% complete
                                • working on the right side of the fairway to the green
                            • Weir Structure Replacement 
                              • Weir - structures that control the water elevations in the lake
                              • Completed on:
                                • Hole #12
                                • Hole #15
                                • Hole #16
                                • Remaining Structures to be replaced:
                                  • Hole #7
                            • Bunker Construction
                              • Finish shaping:
                                • Hole #3 - All bunkers
                                • Hole #4 - Back right bunker
                                • Hole #5 - All Bunkers 
                                • Hole #6 - Fairway Bunker
                              • Better Billy Bunker Liner Installation

                            Upcoming Week Goals:
                            • Complete the Cartpath Installation on hole #14 and start #15
                            • Complete the Irrigation installation on hole #1
                            • Complete the Better Billy Bunker liner installation on hole #3 and #4
                            • Continue to flush and pressurize the Irrigation System
                            • Geotube Installation - complete the right side of the fairway
                            • Modify the current weir structure on the lake of #7 and regrade the drainage swale to the correct elevations.
                            • Fumigation of Tees
                              • Purpose: Eradicate any Nematode population that may still be viable.
                              • Product used: Basamid 
                              • Licensed Applicators: TriEst Ag Group Inc.
                              • Timeframe of Application:
                                • 1st Application: 
                                  • Date: April 8th (1 day)
                                  • Holes: 2 - 8, 11 - 13
                                  • Tarps perforated: April 13th (Monday)
                                  • Tarps removed: April 14th (Tuesday) 
                                • 2nd Application: 
                                  • Date: Tentatively scheduled week of April 20th
                                  • Holes: 1, 9, 10, 14 - 18
                              • Application information:
                                • Once the product is applied to the ground it's then watered in until the soil reaches a specific moisture level. 
                                • Following the watering process a plastic tarp is then laid over top of the application area for a 5 day period. Once the tarps of have been on the ground for a total of a 120 hours the applicators then perforate the tarps and leave them sit for an additional 24 hours. 
                              • Buffer Zones and Re-entry Period: 
                                • There are strict rules regarding buffer zones with is a 30 foot distance from structures and bodies of water.
                                • Outside the drip line of trees.
                                • Once the product is applied there is a re-entry interval of 48 hours. Anyone who is to enter any of the treated areas during this period is required to have the correct personal protective equipment.
                              • Posting Signage in treated areas
                                • Each area will have specific signage signifying that the area has been treated.

                            The Look Ahead:
                            • Grass Installation:  Grass installation will begin the week of April 6th.
                            • The projected opening date is early November.

                            Golf Course Architect, Jason Straka's next scheduled site visits are:   

                            1) April 8th - 10th 

                            2) April 15th - 17th




                            Did you know:  

                            Greens will be firm upon opening due to a lack of maturity.  Greens develop a mat layer, akin to carpet padding.  This is what holds well-struck golf shots.  It takes approximately two to three years for this mat layer to fully develop.


                            Member Course Tours: 

                            Dates & Time:

                            1) April 9th @ 2:30 pm




                            Should you have any questions or comments, please feel free to send them to heron@theoaksclub.com or call the Heron Hotline at 966-6940.



                            *Please know that the entire Heron Golf Course is a construction zone.  To ensure your safety, please do not access the Heron course at any time

                            Progress Video:

                            Password: "oaks"



                            The Heron Implementation Team

                            Friday, March 27, 2015

                            Progress Update #30 - Week 32 - 3/27/15


                            Week 32 Accomplishments:
                            • Irrigation
                              • The  main line, lateral piping, sprinkler installation:  
                                • Hole #9 - 100% complete
                                • Hole #10 - 50% Complete
                            • Cartpath Installation
                              • Completed to date: 
                                • #12 - 85% Complete
                            • Landscape Installation
                              • Small shrub and ornamental grass installation such as Firebush, Bougainvillea, and Muhly grass    
                            • Geotube Installation
                              • Hole #10 - Greens Complex Shoreline 100% complete
                              • Hole #1 - Left side of fairway - 40% complete
                            • Weir Structure Replacement 
                              • Weir - structures that control the water elevations in the lake
                              • Completed on:
                                • Hole #12
                                • Hole #15
                                • Remaining Structures to be replaced:
                                  • Hole #7
                                  • Hole #15
                            • Bunker Construction
                              • Finish shaping:
                                • Hole #3 - All bunkers
                                • Hole #4 - Back right bunker
                                • Hole #5 - All Bunkers 
                                • Hole #6 - Fairway Bunker

                            Upcoming Week Goals:
                              • Continue the landscape installation of the smaller shrubs and grasses on the front 9
                              • Complete the Cartpath Installation on holes #13, and #14
                              • Complete the Irrigation installation on hole #10 & #1
                              • Continue to flush and pressurize the Irrigation System
                              • Geotube Installation - complete the left side of the fairway
                              • Complete the install of all the remaining Weir Structures

                              The Look Ahead:
                              • Grass Installation:  Grass installation will begin the week of April 6th.
                              • Fumigation of Greens Surrounds and Tee Complexes is scheduled to begin the week of April 6th.
                              • Better Billy Bunker Liner installation will begin this coming week.
                              • The projected opening date is early November.

                              Golf Course Architect, Jason Straka's next scheduled site visits are: 
                                
                              1) April 2nd - 3rd
                              2) April 9th - 10th 




                              Did you know:  

                              It takes a minimum of 10 - 12 weeks of ideal growing conditions for sprigged grass to mature to a level that can withstand foot traffic from golfers. This means the course will not be ready for play until 10 - 12 weeks after the last significant area of grass is sprigged.

                              Member Course Tours: 

                              Dates & Time:

                              There are currently no scheduled tours due to cartpath installation taking place on a majority of the golf course. 




                              Should you have any questions or comments, please feel free to send them to heron@theoaksclub.com or call the Heron Hotline at 966-6940.



                              *Please know that the entire Heron Golf Course is a construction zone.  To ensure your safety, please do not access the Heron course at any time

                              Progress Video:

                              Password: "oaks"



                              The Heron Implementation Team