Friday, April 24, 2015

Progress Update #34 - Week 36 - 4/24/2015


Week 36 Accomplishments:
  • Greens:
    • Regrading and checking the rootzone depth:
      • Hole #4 - Complete
      • Hole #5 - Complete
      • Hole #6 - Complete
  • Irrigation
    • Hole #18
      • Mainline pipe has been installed.
      • Sprinklers and Lateral Piping has been installed on tee complex. The areas on the south side of North Creek are currently being installed.
  • Cartpath Installation 
    • #17 - 100% complete 
    • #2 - 50% complete  
  • Geotube Installation
    • Hole #15 - area around the green side bunker is 100% complete
    • Hole #8 - completed the final bag along the green
    • GeoTube is 100% complete for the project!
    • Bunker Construction
      • Finish shaping:
        • Hole #7 - All Fairway Bunkers are complete
      • Better Billy Bunker Liner Installation
        • Hole #6 - All bunkers complete
        • Hole #7 - fairway bunker closest to the green
        • Better Billy Bunker Liner Information:
    • Grassing
      • Order of holes: 3 - 8, 11 - 18, 10, 9, 1, 2
      • Order of installation: 
        • Sodding around bunkers / lake banks / drains
        • Sprigging 
      • Hole #3 
        • Sod is has been laid around all the bunker complexes and lake bank with the Geotube and miscellaneous areas that have a high potential for erosion during a rain event 
        • TifGrand Bermudagrass sod and sprigs have installed around the entire green complex.
        • Celebration sprigs are currently being installed from the bridge to the green.
      • Hole #4
        • Sod has been laid along the lake banks and bunker edges.
        • TifGrand Bermudagrass sod and sprigs has been installed around the entire green complex.
    • Fumigation of Tees:
      • All plastic tarps have been removed from the tees that were fumigated.
      • The remaining tees (#1, #10, #14, #15, #18) are scheduled to be fumigated on May 4th.

    Upcoming Week Goals:
    • Sprig Celebration on Hole #4
    • Complete Cartpath Installation on hole #11 and start #10
    • Complete the installation of Irrigation piping and sprinklers on hole #18
    • Complete the Better Billy Bunker liner installation on hole #7 and #8
    • Complete the modification of the weir structure on the lake of #7 and regrade the drainage swale to the correct elevations.
    • Greens Grassing is scheduled to begin the week of May 12th.


    Golf Course Architect, Jason Straka's next scheduled site visits are:   

    1) April 29th -  May 1st




    Did you know:  

    Irrigation Information:
    The new sprinklers have the capability of dispersing approximately 80 gallons of water per minute. Each station is controlled individually by a computer locating in the Green and Grounds Maintenance building.

      Member Course Tours: 

      Dates & Time:

      Friday, May 1st @ 1:30




      Should you have any questions or comments, please feel free to send them to heron@theoaksclub.com or call the Heron Hotline at 966-6940.



      *Please know that the entire Heron Golf Course is a construction zone.  To ensure your safety, please do not access the Heron course at any time

      Progress Video:

      Password: "oaks"



      The Heron Implementation Team

      Thursday, April 16, 2015

      Progress Update #33 - Week 35 - 4/17/2015


      Week 35 Accomplishments:
      • Greens:
        • Regrading and checking the rootzone depth:
          • Hole #3 - Complete
          • Hole #4 - 80% complete
      • Irrigation
        • Hole #18 - the mainline pipe has been fused and is currently being installed.
      • Cartpath Installation 
        • #16 - 100% complete 
        • #17 - 95 % complete   
      • Geotube Installation
        • Hole #1 
          • Right side of the fairway to the green - 100% complete
      • Bunker Construction
        • Finish shaping:
          • Hole #7 - All Fairway Bunkers are complete
        • Better Billy Bunker Liner Installation
          • Hole #4 - complete
          • Hole #5 - complete
          • Hole #6 - Fairway bunker complete
          • Better Billy Bunker Liner Information:
        • Sand Installation (G-Angle)
          • Holes #3 & #4
      • Grassing
        • Hole #3 
          • Sod is has been laid around all the bunker complexes and lake bank with the Geotube.
          • The entire hole is currently being finished shaped in preparation for sprigging which is schedule to start next Wednesday (April 22nd).
        • Hole #4
          • Sod is being laid along the lake banks and bunker edges and the around entire right front green-side bunker complex.
      • Landscape
        • Hole #4
          • Purple Bougainvillea have been plant around the Bismarck Palms. 
        • Hole #8 
          • Landscape Irrigation has been installed in the bed behind the green
        • Hole #9 
          • Calypso Oleanders have been planted under and around the Sabal palms behind the green-side bunkers.
      • Fumigation of Tees:
        • Product Applied on holes 2, 3, 4, 5, 6, 7, 8, 9, 11, 12, 13, 16, 17
        • The plastic tarps will be perforated on holes 2 - 9 on Sunday for a Monday removal of the tarps. The tarps on holes 11, 12, 13, 16, & 17 will be perforated on Monday with a Tuesday removal.

      Upcoming Week Goals:
      • Sprig Celebration on Hole #3
      • Complete the Cartpath Installation on hole #17
      • Install the Irrigation piping and sprinklers on hole #18
      • Complete the Better Billy Bunker liner installation on hole #6
      • Complete the modification of the weir structure on the lake of #7 and regrade the drainage swale to the correct elevations.
      • Fumigation of Tees
        • Purpose: Eradicate any Nematode population that may still be viable.
        • Product used: Basamid 
        • Licensed Applicators: TriEst Ag Group Inc.
        • Timeframe of Application:
          • 2nd Application: 
            • Date: Monday, May 4th
            • Holes: 1, 10, 14, 15, 18
        • Application information:
          • Once the product is applied to the ground it's then watered in until the soil reaches a specific moisture level. 
          • Following the watering process a plastic tarp is then laid over top of the application area for a 5 day period. Once the tarps of have been on the ground for a total of a 120 hours the applicators then perforate the tarps and leave them sit for an additional 24 hours. 
        • Buffer Zones and Re-entry Period: 
          • There are strict rules regarding buffer zones with is a 30 foot distance from structures and bodies of water.
          • Outside the drip line of trees.
          • Once the product is applied there is a re-entry interval of 48 hours. Anyone who is to enter any of the treated areas during this period is required to have the correct personal protective equipment.
        • Posting Signage in treated areas
          • Each area will have specific signage signifying that the area has been treated.


      Golf Course Architect, Jason Straka's next scheduled site visits are:   

      1) April 22nd - 24th




      Did you know:  

      Grassing Information:
      Following the application / installation of sprigs, it is extremely important to keep the sprigs moist. The irrigation system will run on a continuous basis through-out the day to ensure the sprigs do not dry out.

        Member Course Tours: 

        Dates & Time:

        Wednesday, April 22nd @ 2:30




        Should you have any questions or comments, please feel free to send them to heron@theoaksclub.com or call the Heron Hotline at 966-6940.



        *Please know that the entire Heron Golf Course is a construction zone.  To ensure your safety, please do not access the Heron course at any time

        Progress Video:

        Password: "oaks"



        The Heron Implementation Team

        Friday, April 10, 2015

        Progress Update #32 - Week 34 - 4/10/2015


        Week 34 Accomplishments:
        • Irrigation
          • The  main line, lateral piping, sprinkler installation:  
            • Hole #1 - 100% complete
          • The design is laid out on hole #18
        • Cartpath Installation 
          • #14 - 100% Complete
          • #15 - 95% Complete (Access points left open)
          • #16 - 95% complete    
        • Geotube Installation
          • Hole #1 
            • Left side of fairway - 100% complete
            • Right side of the fairway to the green - 75% complete
        • Weir Structure Replacement 
          • Weir - structures that control the water elevations in the lake
            • Remaining Structure currently being modified:
              • Hole #7
        • Bunker Construction
          • Finish shaping:
            • Hole #4 - All bunkers
            • Hole #6 - All bunkers
          • Better Billy Bunker Liner Installation
        • Grassing
          • Hole #3 
            • Sod is being laid around the fairway bunker complex and lake bank
        • Landscape
          • Hole #1 - Bougainvillea have been planted behind the green. Landscape irrigation has been installed in this bed.
          • Hole #3 - Native grasses planted behind left fairway bunker
          • Hole #4 - Native grasses planted behind the back left bunker. Landscape irrigation has been installed in this bed.
          • Hole #5 - Native grasses planted behind the green-side bunker
          • Hole #8 - 
            • Clusia, Bougainvillea, and native grasses planted behind the tees / roadside. Landscape irrigation has been installed in this bed.
            • Calypso Oleanders and Petite Pink Oleanders have been installed behind the green
          • Hole #9 - 
            • Clusia and Bougainvillea have been planted behind the tee / along the roadside. Landscape irrigation has been installed in this bed.
            • Landscape irrigation has been installed to all the large plant material behind the green.
          • Hole #13 - Shady Lady Olive trees have been planted on the berm behind the green.

        Upcoming Week Goals:
        • Continue the grassing on holes #3 and #4
        • Float / Check green rootzone depth and mix on holes #3 and #4
        • Complete the Cartpath Installation on hole #17
        • Continue to flush irrigation system and setup the satellite box station sequences
        • Complete the Better Billy Bunker liner installation on hole #4 & 5
        • Complete the modification of the weir structure on the lake of #7 and regrade the drainage swale to the correct elevations.
        • Fumigation of Tees
          • Purpose: Eradicate any Nematode population that may still be viable.
          • Product used: Basamid 
          • Licensed Applicators: TriEst Ag Group Inc.
          • Timeframe of Application:
            • 1st Application: 
              • Date: April 13th (1 day)
              • Holes: 2 - 9, 11 - 13
              • Tarps perforated: April 20th (Monday)
              • Tarps removed: April 21st (Tuesday) 
            • 2nd Application: 
              • Date: Tentatively scheduled week of April 20th
              • Holes: 1, 10, 14 - 18
          • Application information:
            • Once the product is applied to the ground it's then watered in until the soil reaches a specific moisture level. 
            • Following the watering process a plastic tarp is then laid over top of the application area for a 5 day period. Once the tarps of have been on the ground for a total of a 120 hours the applicators then perforate the tarps and leave them sit for an additional 24 hours. 
          • Buffer Zones and Re-entry Period: 
            • There are strict rules regarding buffer zones with is a 30 foot distance from structures and bodies of water.
            • Outside the drip line of trees.
            • Once the product is applied there is a re-entry interval of 48 hours. Anyone who is to enter any of the treated areas during this period is required to have the correct personal protective equipment.
          • Posting Signage in treated areas
            • Each area will have specific signage signifying that the area has been treated.


        Golf Course Architect, Jason Straka's next scheduled site visits are:   

        1) April 15th - 17th




        Did you know:  

        Grassing Information:
        Sprigging is the process of removing stems (stolons or rhizomes) from mature bermudagrass stands and replanting the vegetative cuttings in a different location. Any grass that has a lateral growth habit can be established by sprigs, but the aggressive growth rate of bermudagrass makes sprigging a very popular way of establishing new fields. Sprigs are typically from 3 to 5 inches long and contain numerous nodes (i.e. growing points) from which new roots and shoots develop. 

          Member Course Tours: 

          Dates & Time:

          1) April 16th @ 2:30 pm




          Should you have any questions or comments, please feel free to send them to heron@theoaksclub.com or call the Heron Hotline at 966-6940.



          *Please know that the entire Heron Golf Course is a construction zone.  To ensure your safety, please do not access the Heron course at any time

          Progress Video:

          Password: "oaks"



          The Heron Implementation Team

          Friday, April 3, 2015

          Progress Update #31 - Week 33 - 4/3/2015


          Week 33 Accomplishments:
          • Irrigation
            • The  main line, lateral piping, sprinkler installation:  
              • Hole #1 - 35% complete
          • Cartpath Installation 
              • #12 - 100% Complete
              • #13 - 100% Complete
              • #14 - 85% Complete    
          • Geotube Installation
            • Hole #1 
              • Left side of fairway - 90% complete
              • working on the right side of the fairway to the green
          • Weir Structure Replacement 
            • Weir - structures that control the water elevations in the lake
            • Completed on:
              • Hole #12
              • Hole #15
              • Hole #16
              • Remaining Structures to be replaced:
                • Hole #7
          • Bunker Construction
            • Finish shaping:
              • Hole #3 - All bunkers
              • Hole #4 - Back right bunker
              • Hole #5 - All Bunkers 
              • Hole #6 - Fairway Bunker
            • Better Billy Bunker Liner Installation

          Upcoming Week Goals:
          • Complete the Cartpath Installation on hole #14 and start #15
          • Complete the Irrigation installation on hole #1
          • Complete the Better Billy Bunker liner installation on hole #3 and #4
          • Continue to flush and pressurize the Irrigation System
          • Geotube Installation - complete the right side of the fairway
          • Modify the current weir structure on the lake of #7 and regrade the drainage swale to the correct elevations.
          • Fumigation of Tees
            • Purpose: Eradicate any Nematode population that may still be viable.
            • Product used: Basamid 
            • Licensed Applicators: TriEst Ag Group Inc.
            • Timeframe of Application:
              • 1st Application: 
                • Date: April 8th (1 day)
                • Holes: 2 - 8, 11 - 13
                • Tarps perforated: April 13th (Monday)
                • Tarps removed: April 14th (Tuesday) 
              • 2nd Application: 
                • Date: Tentatively scheduled week of April 20th
                • Holes: 1, 9, 10, 14 - 18
            • Application information:
              • Once the product is applied to the ground it's then watered in until the soil reaches a specific moisture level. 
              • Following the watering process a plastic tarp is then laid over top of the application area for a 5 day period. Once the tarps of have been on the ground for a total of a 120 hours the applicators then perforate the tarps and leave them sit for an additional 24 hours. 
            • Buffer Zones and Re-entry Period: 
              • There are strict rules regarding buffer zones with is a 30 foot distance from structures and bodies of water.
              • Outside the drip line of trees.
              • Once the product is applied there is a re-entry interval of 48 hours. Anyone who is to enter any of the treated areas during this period is required to have the correct personal protective equipment.
            • Posting Signage in treated areas
              • Each area will have specific signage signifying that the area has been treated.

          The Look Ahead:
          • Grass Installation:  Grass installation will begin the week of April 6th.
          • The projected opening date is early November.

          Golf Course Architect, Jason Straka's next scheduled site visits are:   

          1) April 8th - 10th 

          2) April 15th - 17th




          Did you know:  

          Greens will be firm upon opening due to a lack of maturity.  Greens develop a mat layer, akin to carpet padding.  This is what holds well-struck golf shots.  It takes approximately two to three years for this mat layer to fully develop.


          Member Course Tours: 

          Dates & Time:

          1) April 9th @ 2:30 pm




          Should you have any questions or comments, please feel free to send them to heron@theoaksclub.com or call the Heron Hotline at 966-6940.



          *Please know that the entire Heron Golf Course is a construction zone.  To ensure your safety, please do not access the Heron course at any time

          Progress Video:

          Password: "oaks"



          The Heron Implementation Team

          Friday, March 27, 2015

          Progress Update #30 - Week 32 - 3/27/15


          Week 32 Accomplishments:
          • Irrigation
            • The  main line, lateral piping, sprinkler installation:  
              • Hole #9 - 100% complete
              • Hole #10 - 50% Complete
          • Cartpath Installation
            • Completed to date: 
              • #12 - 85% Complete
          • Landscape Installation
            • Small shrub and ornamental grass installation such as Firebush, Bougainvillea, and Muhly grass    
          • Geotube Installation
            • Hole #10 - Greens Complex Shoreline 100% complete
            • Hole #1 - Left side of fairway - 40% complete
          • Weir Structure Replacement 
            • Weir - structures that control the water elevations in the lake
            • Completed on:
              • Hole #12
              • Hole #15
              • Remaining Structures to be replaced:
                • Hole #7
                • Hole #15
          • Bunker Construction
            • Finish shaping:
              • Hole #3 - All bunkers
              • Hole #4 - Back right bunker
              • Hole #5 - All Bunkers 
              • Hole #6 - Fairway Bunker

          Upcoming Week Goals:
            • Continue the landscape installation of the smaller shrubs and grasses on the front 9
            • Complete the Cartpath Installation on holes #13, and #14
            • Complete the Irrigation installation on hole #10 & #1
            • Continue to flush and pressurize the Irrigation System
            • Geotube Installation - complete the left side of the fairway
            • Complete the install of all the remaining Weir Structures

            The Look Ahead:
            • Grass Installation:  Grass installation will begin the week of April 6th.
            • Fumigation of Greens Surrounds and Tee Complexes is scheduled to begin the week of April 6th.
            • Better Billy Bunker Liner installation will begin this coming week.
            • The projected opening date is early November.

            Golf Course Architect, Jason Straka's next scheduled site visits are: 
              
            1) April 2nd - 3rd
            2) April 9th - 10th 




            Did you know:  

            It takes a minimum of 10 - 12 weeks of ideal growing conditions for sprigged grass to mature to a level that can withstand foot traffic from golfers. This means the course will not be ready for play until 10 - 12 weeks after the last significant area of grass is sprigged.

            Member Course Tours: 

            Dates & Time:

            There are currently no scheduled tours due to cartpath installation taking place on a majority of the golf course. 




            Should you have any questions or comments, please feel free to send them to heron@theoaksclub.com or call the Heron Hotline at 966-6940.



            *Please know that the entire Heron Golf Course is a construction zone.  To ensure your safety, please do not access the Heron course at any time

            Progress Video:

            Password: "oaks"



            The Heron Implementation Team

            Friday, March 20, 2015

            Progress Update #29 - Week 31 - 3/20/2015


            Week 31 Accomplishments:
            • Earthmoving / Rough Shaping
              • Hole #1 - Fairway - 100% complete
            • Irrigation
              • The  main line, lateral piping, sprinkler installation:  
                • Hole #9 - 90% complete
                • Hole #17 - 100% complete
            • Cartpath Installation
              • Completed to date: 
                • #3 - #8 - 100%
                • #11 - 85% (Tee Complex remain)
                • #12 - started this morning
                • #13 - 50% (completed from tees to bridge)
            • Landscape Installation
              • Bismarck Palm Installation - Holes #5, #9, and #18
              • Live Oaks - #1, #8, #17, #18
              • Hong Kong Orchid Trees - Hole #2, #4, #8, #9, #17, #18
              • The larger plant material is being installed first due to the use of the heavy machinery.    
            • Geotube Installation
              • Hole #9 - Greens Complex Shoreline is 100% complete
              • Hole #10 - Greens Complex Shoreline 50% complete
            • Weir Structure Replacement 
              • (structures that control the water elevations in the lake)
              • Completed on:
                • Hole #5 / 6
                • Hole #8
                • Remaining Structures to be replaced:
                  • Hole #7
                  • Hole #12
                  • Hole #15
                  • Hole #16
            • Bunker Construction
              • Finish shaping has begun on hole #3. This phase takes place right before grassing is to begin.
              • Following the approval from the Course Architect, a bunker liner will be installed which aides in drainage during heavy rain events.

            Upcoming Week Goals:
              • Continue the landscape installation of the Oaks and Flowering Trees
              • Complete the Cartpath Installation on holes #12, #13, and #14
              • Complete the Irrigation installation on hole #10
              • Continue to flush and pressurize the Irrigation System
              • Continue to install new Weir Structures (Controls the water level in the lakes)
              • Geotube Installation - Start  #1 green
              • Complete the install of all the remaining Weir Structures

              The Look Ahead:
              • Grass Installation: With the assistance of our FRIEND Mother Nature we are hopeful to begin grass installation the week of April 6th.
              • Fumigation of Greens Surrounds and Tee Complexes is scheduled to begin the week of April 6th.
              • Bunker Construction will begin at the end of March.
              • The projected opening date is early November.

              Golf Course Architect, Jason Straka's next scheduled site visits are: 
                
              1) March 27th - 28th 




              Did you know:  

              The pressure in the irrigation sprinklers are set at 80 - 85 psi. The pressure coming out of the the pump-station is set at 110 psi.

              Member Course Tours: 

              Dates & Time:

              There are currently no scheduled tours due to cartpath installation taking place on a majority of the golf course. 




              Should you have any questions or comments, please feel free to send them to heron@theoaksclub.com or call the Heron Hotline at 966-6940.



              *Please know that the entire Heron Golf Course is a construction zone.  To ensure your safety, please do not access the Heron course at any time

              Progress Video:

              Password: "oaks"



              The Heron Implementation Team

              Friday, March 13, 2015

              Progress Update #28 - Week 30 - 3/13/2015


              Week 30 Accomplishments:
              • Earthmoving / Rough Shaping
                • Hole #9 
                  • Tee Complex - 100% complete
                • Hole #1 - Fairway - 85% complete
              • Irrigation
                • The  main line, lateral piping, sprinkler installation:  
                  • Hole #9 - Mainline pipe has been installed
                  • Hole #17 - 80% complete
              • Cartpath Installation
                • Completed to date: 
                  • #3 - 100%
                  • #7 - 95%
                  • #8 - 100%
              • Landscape Installation
                • Sabal Palm Installation - Holes #5, #8, #9, #15, #17
                • Live Oaks - 2 live oaks planted behind the green on hole #7
                • Hong Kong Orchid Trees - Hole #8   
              • Geotube Installation
                • Hole #15 - Greenside is nearly complete. A new weir structure has to be installed first to complete the GeoTube.
                • Hole #9 - Greens Complex Shoreline is 85% complete
                • Remaining Areas:
                  • Hole #1 - Left and right shorelines along the fairway
                  • Hole #10 - Greens Complex Shoreline

              Upcoming Week Goals:
                • Continue the landscape installation of the Oaks and Flowering Trees 
                • Complete the Cartpath Installation on holes #11 and #12
                • Complete the Irrigation installation on hole #17 and start #9
                  • A portion of the system will be pressurized in the middle of the week.
                • Continue Earthwork plan on hole #1
                • Start to install new Weir Structures (Controls the water level in the lakes)
                • Geotube Installation - Start  #10 green

                The Look Ahead:
                • Grass Installation: With the assistance of our FRIEND Mother Nature we are hopeful to begin grass installation in the middle to latter part of March or the early part of April.
                • Bunker Construction will begin at the end of March.
                • The projected opening date is early November.

                Golf Course Architect, Jason Straka's next scheduled site visits are: 
                  
                1) March 16th - 18th 




                Did you know:  

                The height of the new sabal palms being installed range from 12 - 16 feet tall.

                Member Course Tours: 

                Dates & Time:

                1) Wednesday, March 18th @ 9:30 am 



                Meeting Location: 


                Golf Cart Staging Area out side the Golf Shop entrance 

                Registration Information:
                Registration can be accomplished by utilizing the event sign-up section on ForeTees via the Club website or by calling the Golf Shop at 966-2191. Sign-ups are limited to 20 with a waiting list once registration is full. 




                Should you have any questions or comments, please feel free to send them to heron@theoaksclub.com or call the Heron Hotline at 966-6940.



                *Please know that the entire Heron Golf Course is a construction zone.  To ensure your safety, please do not access the Heron course at any time

                Progress Video:

                Password: "oaks"



                The Heron Implementation Team