Saturday, July 18, 2015

Progress Update #46 - Week 48 - 7/18/2015


Week 48 Accomplishments 

  • Grassing:
    • Hole #18 - All areas are complete
    • Hole #1 - Sod has been laid around of the lake bank along the tee complex and other specific areas
    • Hole #9 - Sod has been laid around the bunkers and lake bank at the green complex
    • Bunker Construction:
      • Hole #9
        • Green-side - 100% complete
      • Hole #10
        • Fairway and Green-side bunkers are shaped and drainage piping and gravel are being installed.
    • Landscape Installation
      • Oleanders and Fountain Grass have been installed under the 8 Shady Lady Olive trees to the left of #10 Tees.
      • Bougainvilleas have been installed behind #10 tees around 3 Bismarck palms.
      • 2 Live Oaks have been installed behind and to the left of #10 green 

        Upcoming Week Goals:
        • Grassing: 
          • Due to the inclement weather on Thursday and Friday, grassing of the below areas have been rescheduled for Monday, July 20th
            • Holes #1 - Sod and Sprig the Tee Complex 
            • Hole #9 - Sod and Sprig Green surrounds and fairway area of the green side of the lake
            • Hole #10 - Sod and Sprig Tee complex 
          • Hole #10 & #11 tee complex - complete later in the week
        • Bunker Construction:
          • Complete Better Billy Bunker liner and sand installation on holes #10, #9 Fairway, and #1 Fairway.

        Did you know:

        Since Monday, July 13th, The Oaks Club has received approximately 4.25 inches of rain as of Friday, July 17th. 


        Member Course Tours:

        Wednesday, July 29th @ 1:30 pm



        Should you have any question or comments, please feel free to send them to heron@theoaksclub.com or call the Heron Hotline at 966-6940 



        *Please know that the entire Heron Golf Course is a construction zone. To Ensure your safety, please do not access the Heron course at any time. Should you see anyone out walking or driving on the course not accompanied by Management, please notify the Golf Shop or Security.



        Progress Video:

        Due to inclement weather on Thursday and Friday, a Progress Video will be produced and distributed on Monday, July 20th. 


        The Heron Implementation Team

        Friday, July 10, 2015

        Progress Update #45 - Week 47 - 7/10/15


        Week 47 Accomplishments 

        • Grassing:
          • Hole #18 - All sod work will be completed by Saturday, 7/11/15.
          • Hole #1 - Sod has been laid on 75% of the lake bank along the tee complex
          • Bunker Construction:
            • Hole #18
              • Fairway
                • All bunkers have Better Billy Bunker liner installed
                • remaining bunkers are in the process of having bunker sand installed
            • Hole #9
              • Green-side
                • Drainage and Gravel installation is 85% complete
          • Landscape Installation
            • Native grasses installed along the upper portion to of the fairway bunkers on the left side.
            • 8 Shady Lady Olive trees have been installed as a buffer from #10 tee and the driving range buffer
            • Ferns are being installed under the large oaks behind #17 green

              Upcoming Week Goals:
              • Grassing: 
                • Hole #18 - Sprig the remaining areas on Monday, 7/13
                • Holes #1 - Sod and Sprig the Tee Complex 
                • Hole #9 - Sod and Sprig Green surrounds and fairway area of the green side of the lake
                • Hole #10 - Sod and Sprig Tee complex 
              • Bunker Construction:
                • Hole #18 - Complete the remaining bunkers
                • Hole #10 - Start the shaping, drainage, and bunker liner installation
              • Finish Shaping
                • Hole #10 / #9 / #1 - Continue to box blade in preparation for grassing
              • Landscape Installation will continue at the beginning of the week

              Did you know:

              The Shady Lady Olive Tree can reach 30 feet in height and are considered a "non-messy" tree. 


              Member Course Tours:

              Tuesday, July 14th @ 10:00 am



              Should you have any question or comments, please feel free to send them to heron@theoaksclub.com or call the Heron Hotline at 966-6940 



              *Please know that the entire Heron Golf Course is a construction zone. To Ensure your safety, please do not access the Heron course at any time. Should you see anyone out walking or driving on the course not accompanied by Management, please notify the Golf Shop or Security.



              Progress Video:

              Click Here to view the Progress Video
              Password: "oaks"


              The Heron Implementation Team

              Friday, July 3, 2015

              Progress Update #44 - Week 46 - 7/3/2015


              Week 46 Accomplishments 

              • Grassing:
                • Hole #15 is completely grassed
                • Tee complex on #9 is 95% Complete & Hole #18 is 100% complete
              • Bunker Construction:
                • Hole #18
                  • Green-side  
                    • Better Billy Bunker Liner and Sand installed
                  • Fairway
                    • 2 bunkers have Better Billy Bunker installed
                    • remaining bunkers are in the process of being shaped, drainage installation, and / or Better Billy Bunker Liner being installed.

                Upcoming Week Goals:
                • Grassing: 
                  • Hole #18 - Complete the remaining areas  
                • Bunker Construction:
                  • Hole #18 - Complete the remaining bunkers
                  • Hole #10 - Start the shaping, drainage, and bunker liner installation
                • Finish Shaping
                  • Hole #10 / #9 / #1 - Continue the bulldozer work on these three holes  

                Did you know:

                It takes a golf course sprinkler approximately 3 minutes to make a complete 360 degree rotation.


                Member Course Tours:

                No Tours are scheduled the week of July 6th



                Should you have any question or comments, please feel free to send them to heron@theoaksclub.com or call the Heron Hotline at 966-6940 



                *Please know that the entire Heron Golf Course is a construction zone. To Ensure your safety, please do not access the Heron course at any time. Should you see anyone out walking or driving on the course not accompanied by Management, please notify the Golf Shop or Security.



                Progress Video:

                Click Here to view the Progress Video



                The Heron Implementation Team

                Friday, June 26, 2015

                Progress Update #43 - Week 45 - 6/26/2015


                Week 45 Accomplishments 

                • Grassing:
                  • All Greens, Collars, Approaches, and Chipping areas have been grassed
                    • Greens = TifEagle Bermuda
                    • Collars, Approaches, and Chipping Areas = TifGrand Bermuda
                • Bunker Construction:
                  • Hole #15
                    • Green-side Bunker is complete
                    • Fairway Waste Bunker is 90% complete
                • Cartpath Installation:
                  • All Cartpaths are complete

                  Upcoming Week Goals:
                  • Grassing: 
                    • Hole #15 - Monday & Tuesday
                    • Hole #18 Tee Complex - Wednesday or Thursday
                    • Hole #9 Tee Complex - Wednesday or Thursday
                  • Bunker Construction:
                    • Hole #18 - Complete the Better Billy Bunker Liner installation and install the G-Angle Bunker Sand

                  Did you know:

                  • The Project remains on Time and on Budget!
                  • All areas which are utilized for material storage and/or course entry points will be refurbished to a better condition than when they were originally used for prior to construction beginning. The contractor is obligated per the contract with Club to do so at the conclusion of the project.


                  Member Course Tours:

                  Wednesday, July 1st @ 1:30 PM


                  Should you have any question or comments, please feel free to send them to heron@theoaksclub.com or call the Heron Hotline at 966-6940 



                  *Please know that the entire Heron Golf Course is a construction zone. To Ensure your safety, please do not access the Heron course at any time. Should you see anyone out walking or driving on the course not accompanied by Management, please notify the Golf Shop or Security.



                  Progress Video:

                  Click Here to view the Progress Video
                  Password = oaks


                  The Heron Implementation Team

                  Friday, June 19, 2015

                  Progress Update #42 - Week 44 - 6/19/2015


                  Week 44 Accomplishments 

                  • Bunker Construction:
                    • Hole #15 
                      • Green-side Bunker -  ready for drainage installation and then Better Billy Bunker liner installation
                      • Waste Bunker along the fairway is 60% complete
                    • Hole #18 - Green-side bunkers are being shaped 
                  • Grassing:
                    • 12 holes are 95% grassed or fully complete.
                    • Remaining Order of holes:16, 15, 18, 10, 9, 1, 2 
                    • Holes #17
                      • All areas have been grassed 
                  • Cartpath Installation:
                    • Hole #1 & #2 - Complete

                    Upcoming Week Goals:
                    • Grassing: 
                      • Celebration Bermudagrass
                        • Complete hole #16
                      • TifGrand Bermudagrass
                        • Complete holes 15, 18, 10, 9, 1, and 2
                      • TifEagle (Greens)
                        • Complete holes 15, 18, 10, 9, 1, and 2
                    • Bunker Construction:
                      • Install drainage and Better Billy Bunker in the green-side bunker on #15
                      • Continue Bunker shaping around the #18 Green

                    Did you know:

                    The large concrete structure located on hole #2 was intended to be used as replacement for the weir structure in the lake on hole #7. Instead the structure that is there was modified and thus the structure on hole #2 is going to be returned.


                    Member Course Tours:

                    Wednesday, June 24th @ 10:30 AM



                    Should you have any question or comments, please feel free to send them to heron@theoaksclub.com or call the Heron Hotline at 966-6940 



                    *Please know that the entire Heron Golf Course is a construction zone. To Ensure your safety, please do not access the Heron course at any time. Should you see anyone out walking or driving on the course not accompanied by Management, please notify the Golf Shop or Security.



                    Progress Video:

                    Click Here to view the Progress Video
                    Password = oaks


                    The Heron Implementation Team

                    Friday, June 12, 2015

                    Progress Update #41 - Week 43 - 6/12/15


                    Week 43 Accomplishments 

                    • Greens:
                      • Regrading and checking the rootzone depth
                        • Holes 1, 2, 9, & 10 - Complete
                    • Bunker Construction:
                      • Hole #17 Fairway Bunkers - Drainage installation and Better Billy Bunker liner is either in the process if being complete or is complete.
                    • Grassing:
                      • Order of holes: 3 - 8, 11 - 18, 10, 9, 1, 2 
                      • Order of installation 
                        • Sodding around bunkers / lake banks / drains
                        • TifGrand Bermuda - Collars, Approaches, and Chipping areas
                        • Celebration Bermuda Sprigs - Fairways, Roughs, and Tees
                      • Greens - Phase #2 of 3 - #11, 12, 13, 14, 16, & 17 = complete
                      • Holes #14
                        • All areas have been grassed 

                      Upcoming Week Goals:
                      • Grassing: 
                        • Celebration Bermudagrass  
                          • Sprig and Sod Holes #16 & #17
                      • Bunker Construction:
                        • Install drainage and Better Billy Bunker in the green-side bunker on #15
                        • Install drainage in the waste bunker on the left side of hole #15

                      Did you know:

                      The first and second phase of greens grassing are 81,056 square feet or 1.86 acres. The old Heron greens were slightly over 130,680 square feet or 3 acres.


                      Member Course Tours:

                      Wednesday, June 17th @ 1:30 PM



                      Should you have any question or comments, please feel free to send them to heron@theoaksclub.com or call the Heron Hotline at 966-6940 



                      *Please know that the entire Heron Golf Course is a construction zone. To Ensure your safety, please do not access the Heron course at any time. Should you see anyone out walking or driving on the course not accompanied by Management, please notify the Golf Shop or Security.



                      Progress Video:

                      Click Here to view the Progress Video




                      The Heron Implementation Team

                      Friday, June 5, 2015

                      Progress Update #40 - Week 42 - 6/5/2015


                      Week 42 Accomplishments 

                      • Greens:
                        • Regrading and checking the rootzone depth
                          • Holes 16, 17, & 18 - Complete
                      • Bunker Construction:
                        • Hole #16 & #17 Greenside Bunkers - Drainage installation and Better Billy Bunker liner installed in the green-side bunker
                      • Grassing:
                        • Order of holes: 3 - 8, 11 - 18, 10, 9, 1, 2 
                        • Order of installation 
                          • Sodding around bunkers / lake banks / drains
                          • TifGrand Bermudagrass - Collars, Approaches, and Chipping areas
                          • Celebration Sprigs
                        • Holes #12
                          • All areas have been grassed with the exception of the green
                        • Holes #14, 16, & 17
                          • TifGrand Bermudagrass installed - Collars, Approach Areas, and Chipping Areas

                        Upcoming Week Goals:
                        • Grassing: 
                          • Celebration Bermudagrass  
                            • Sprig and Sod Holes #14 & half  of #17
                          • TifEagle - Greens
                            • Holes #11, 12, 13, 14, 16, & 17
                        • Bunker Construction:
                          • Install Drainage and Better Billy Bunker in the fairway bunkers on #17 and the green-side bunker on #15


                        Did you know:

                        The course will be Cartpath Only for at least 3 months to allow the turf to fully mature during the slower growing period (Winter Months).


                        Member Course Tours:

                        Wednesday, June 10th @ 1:30 PM



                        Should you have any question or comments, please feel free to send them to heron@theoaksclub.com or call the Heron Hotline at 966-6940 



                        *Please know that the entire Heron Golf Course is a construction zone. To Ensure your safety, please do not access the Heron course at any time. Should you see anyone out walking or driving on the course not accompanied by Management, please notify the Golf Shop or Security.



                        Progress Video:

                        Click Here to view the Progress Video
                        Password = "oaks"



                        The Heron Implementation Team