Progress Update #51 - Week 53 - 8/22/15


Week 53  

  • The contractor continues to work on punch list tasks.
    • Southeastern Golf will assist with erosion repair after they have completed their punch list task.
  • The Green and Grounds team mowed #15 fairway for the first time since the grass installation
    • The fairways, tees, and approaches on holes 3-8, 11-17 are being mowed on a routine basis.
  • All the greens were topdressed and also aerated.
  • This week we will begin to aerating the fairway on hole #3.

Did you know:

There were over 1,800 landscape plants installed on the berm that separates hole #18 from driving range.

Member Course Tours:

Wednesday, August 26th @ 1:30 pm


Should you have any question or comments, please feel free to send them to heron@theoaksclub.com or call the Heron Hotline at 966-6940 



*Please know that the entire Heron Golf Course is a construction zone. To Ensure your safety, please do not access the Heron course at any time. Should you see anyone out walking or driving on the course not accompanied by Management, please notify the Golf Shop or Security.



Progress Video:

Click Here to view the Week #53 Progress



The Heron Implementation Team

Friday, August 14, 2015

Progress Update #50 - Week 52 - 8/14/15


Week 52 Accomplishments 

  • Grassing = 100% Complete
  • Bunker Construction = 100% Complete



Upcoming Week Goals:
  • Contractor is to start the punch list 
  • Start the construction of the Heron Putting green which is apart of the Member approved plan.


    Did you know:

    • The greens are grassed with TifEagle Bermudagrass
    • The collars and chipping surrounds are grassed with TifGrand Bermudagrass
    • The fairways, tees, and roughs are grassed with Celebration Bermudagrass
    • There are several miscellaneous rough areas that are grassed with Argentine Bahiagrass



    Member Course Tours:

    Wednesday, August 26th @ 1:30 pm


    Should you have any question or comments, please feel free to send them to heron@theoaksclub.com or call the Heron Hotline at 966-6940 



    *Please know that the entire Heron Golf Course is a construction zone. To Ensure your safety, please do not access the Heron course at any time. Should you see anyone out walking or driving on the course not accompanied by Management, please notify the Golf Shop or Security.



    Progress Video:

    Click Here to view the Week #50 Progress



    The Heron Implementation Team

    Friday, August 7, 2015

    Progress Update #49 - Week 51 - 8/7/15


    Week 51 Accomplishments 

    • Grassing:
      • Hole #1 - 95% complete
      • Hole #9 - 100% complete
      • Hole #2 - Sod has been laid around the tee complex and continues around the bunkers
    • Bunker Construction:
      • Hole #1 - 100% complete
      • Hole #2 - 90% complete (sand installation will be completed on Saturday, August 8th)

    Upcoming Week Goals:
    • Grassing: 
      • Hole #2 - complete the remaining grass installation by Wednesday, August 12th.
    • Southeastern Golf will begin the punch-list that has been created by Jason Straka (Course Architect) and Joe Voss (Project Manager).


    Did you know:

    A year ago the 2nd grass eradication application was being applied to the course.


    Member Course Tours:

    Wednesday, August 12th @ 1:30 PM


    Should you have any question or comments, please feel free to send them to heron@theoaksclub.com or call the Heron Hotline at 966-6940 



    *Please know that the entire Heron Golf Course is a construction zone. To Ensure your safety, please do not access the Heron course at any time. Should you see anyone out walking or driving on the course not accompanied by Management, please notify the Golf Shop or Security.



    Progress Video:

    Click Here to view the Week #50 Progress



    The Heron Implementation Team