The Oaks Club - Heron Golf Course Renovation
Week 1 Accomplishments:
- Rototilling
- Holes 3, 4, & 5 are 85 % complete. The perimeters of each hole will remain with turf as an added erosion barrier
- Greens
- Soil is being removed and stockpiled for tees
- Existing soil has been excavated on holes 3, 4, and 5
- Erosion Control
- Silt Fence Installation
- Completed on Holes 3 - 9
- Turbidity Barrier Installation
- Installed in #3 lake
- Earthmoving / Shaping
- started on hole #4
- Existing Irrigation Removal
- Completed on holes 3 - 9
Upcoming Week Goals:
- Complete Silt Fence Installation on entire front nine
- Start initial clearing plan on holes 3 - 5. (Approved permit from Sarasota County)
- Complete irrigation head extraction on holes 1 & 2
- Continue to install tree protection fencing
- Earthmoving / shaping on holes #3 & #4.
Click here for a brief video
Should you have any questions or comments, please feel free to send them to heron@theoaksclub.com or call the Heron Hotline at 966-6940.
The Heron Implementation Team