Tuesday, August 26, 2014

Progress Update #3 - Week 2 - 8/25/2014

The Oaks Club - Heron Golf Course Renovation


Week 1 Accomplishments:
  • Rototilling 
    • Holes 3, 4, & 5 are 85 % complete. The perimeters of each hole will remain with turf as an added erosion barrier
  • Greens 
    • Soil is being removed and stockpiled for tees
    • Existing soil has been excavated on holes 3, 4, and 5
  • Erosion Control
    • Silt Fence Installation
      • Completed on Holes 3 - 9
    • Turbidity Barrier Installation
      • Installed in #3 lake
  • Earthmoving / Shaping
    • started on hole #4
  • Existing Irrigation Removal
    • Completed on holes 3 - 9


Upcoming Week Goals:
  • Complete Silt Fence Installation on entire front nine
  • Start initial clearing plan on holes 3 - 5. (Approved permit from Sarasota County)
  • Complete irrigation head extraction on holes 1 & 2
  • Continue to install tree protection fencing
  • Earthmoving / shaping on holes #3 & #4. 

Please click on the below link to view a progress update video:

Click here for a brief video


Should you have any questions or comments, please feel free to send them to heron@theoaksclub.com or call the Heron Hotline at 966-6940.

The Heron Implementation Team